|
Williamsburg Bridge Contract #8
Rank #10
Cost: $173 million
When it became apparent in the early 1980s that the Williamsburg
Bridge would either have to be reconstructed or replaced,
the New York City Department of Transportation chose the former.
Built in 1903, the 2,793-ft. bridge was the longest suspension
bridge in the world. Because of its historical and architectural
value, the city decided to reconstruct the structure rather
than replace it. Work on the $600 million project began in
1991.
In 2003 Koch Skanska of Carteret, N.J., began work on a $173
million contract for the rehabilitation of the main spans
of the bridge - the latest contract awarded for the project.
The project, which is scheduled to finish in early 2006, will
include the rehabilitation of the tower bearings, truss system,
steel structure of all eight towers and work on the north
comfort station houses. Also planned is the replacement or
adjustment of the cable suspenders, installation of maintenance
travelers (inspection platforms) under the main span and painting
of the stiffening trusses.
Architectural work will include the restoration of decorative
lights and the Brooklyn granite stone monument. Work inside
the anchorage houses on both the Manhattan and Brooklyn sides
will include the construction of new stairs, a hoisting system,
oiling of platforms, and ventilation and lighting. The project
will also include the installation of an Intelligent Transportation
System.
During the rehabilitation and seismic retrofitting of the
bridge, the 350-ft.-tall main towers will be strengthened
with 3.3 million lbs. of steel, and the intermediate towers
will be strengthened with 1.8 million lbs. of steel. The two
main stiffening trusses will be de-leaded and repainted, totaling
approximately 675,000 sq. ft.
The de-leading and repainting has an aggressive schedule
that requires completion within six months. To meet the tight
schedule, Koch Skanska has planned work activities 24 hours
a day, 7 days a week.
The bridge spans the East River between the boroughs of Brooklyn
and Manhattan and carries more than 100,000 vehicles and 90,000
people on the subway every day. And the project must be completed
with minimal interference with traffic flow.
The transportation department has instituted traffic mitigation
measures such as installing message signs on nearby roadways,
including the Brooklyn-Queens Expressway, to provide motorists
with real-time traffic conditions. It also has dedicated a
tow truck service to ensure quick response in clearing disabled
vehicles from the bridge.
In addition, Koch Skanska faces severe penalties for delays
in activities that affect vehicular traffic. The milestone
for the reopening of the lane closures utilized for the truss
painting includes a $50,000-a-day penalty with no maximum
limit for late opening.
Back
to list >>
|