|
500-Megawatt, Combined-Cycle Power Plant
Rank #6
Cost: $245 million
In recent years blackouts have spawned the need for new power
plants and work for the construction industry in New York.
In 2003, Slattery Skanska and Gottlieb Skanska began construction
on a state-of-the-art combined-cycle plant in the Astoria
section of Queens on a four-acre site next to the existing
Charles M. Poletti Generating Station. The new plant will
add 500 MW to New York's power supply.
The project team is responsible for the overall construction
of the plant, including the erection of a 97,000-sq.-ft.,
two-story building to house all of the sophisticated plant
equipment. Slattery Skanska will perform the installation,
testing and commissioning of all equipment, including two
dual-fuel Frame 7FA Combustion Turbine Generators and one
D11 Steam Turbine Generator, all manufactured by General Electric.
The team will install, test and commission two heat-recovery
steam generators manufactured by Vogt-NEM Inc. Each generator
will feature a 160-ft.-tall steel stack.
The plant will burn natural gas, with low-sulfur oil as a
backup, and use a sophisticated combined-cycle technology
that is cleaner and more efficient than most plants. The plant
will be equipped with the most advanced Selective Catalytic
Reduction emission controls.
Slattery Skanska will directly perform the civil, structural
and mechanical work, which includes installation of 110,000
lin. ft. of process piping; 500 monitoring instruments; a
one-million-gallon water tank; and a 32-cell, air-cooled condenser.
The project team will also manage the installation of the
plant's electrical systems, which include a digital control
system, three step-up transformers, switch gear, 1.4 million
lin. ft. of cable, 215,000 lin. ft. of conduit and 26,000
lin. ft. of cable tray.
Under a separate contract Slattery Skanska's subsidiary,
Underpinning & Foundation Skanska, drove approximately
2,500 steel H-piles averaging 40 ft. long and drilled 37 24-in.
and 30-in. caissons into rock.
Workers are performing some field activities in shifts around
the clock. As many as 650 workers, representing 15 local labor
unions, will be employed during construction.
All construction equipment and vehicles onsite will be required
to use low-sulfur fuel and particulate-control technology
to limit emissions and protect air quality.
Back
to list >>
|