|
Newtown Creek Water Pollution Control Plant
Rank #4 (Tied)
Cost: $493 million
A joint venture of Slattery Skanska, Picone/McCullagh JV
and Perini Corp. began work in August to upgrade New York
City's largest wastewater treatment facility.
Work on the Newtown Creek Water Pollution Control Plant in
the Greenpoint section of Brooklyn, includes expanding the
plant from 16 treatment areas to 24.
The job will involve extensive new construction of piping,
aeration and sedimentation tanks and a new control building,
as well as upgrading of existing plant components. In addition,
the new and existing sections must be integrated.
Skanska USA Civil companies Slattery Skanska and Gottlieb
Skanska and Underpinning & Foundation Skanska will do
45 percent of the work, Picone/McCullagh JV will do 30 percent
and Perini Corp. will do 25 percent.
This contract is one of many that have been awarded as part
of a massive effort to upgrade Newtown Creek to bring it into
compliance with secondary treatment requirements mandated
by the federal Clean Water Act. The law was enacted to maintain
the quality of the nation's water supplies and eliminate the
discharge of harmful materials into water.
The New York City Department of Environmental Protection
has until December 2007 to provide secondary treatment of
all sewage at the facility. When completed, the 53-acre facility
will be the last of the city's 14 treatment plants to be upgraded
to meet federal standards.
The work includes demolishing and reconstructing four aeration
tanks and four sedimentation tanks at the Central Battery
area of the plant. Modifications to eight aeration and eight
sedimentation tanks in the South Battery area will also be
undertaken. The contract requires construction of new foundations
and piers for support of air main as well as odor-control
piping at both locations.
Work on the new North Battery tanks includes construction
of new grit and aeration tanks and sedimentation tanks. An
influent feed system will also be installed, which includes
96-ft. of encased piping. The new North Battery tanks will
measure approximately 310,000 sq. ft. and require more than
85,000 cu. yds. of concrete for construction. A new 40,000-sq.-ft.
control building will be constructed to service the new and
modified tanks.
Mechanical work includes installation and procurement of
eight new process air blowers in the existing main building
and utility work throughout the construction area.
Back
to list >>
|