|
Interchange 8 Reconstruction
Rank #16
Cost: $187 million
It took almost three years, but the $187 million, 3-mi. Interchange
8 Reconstruction project has been completed.
The project involved the construction of new connecting roadways
linking Interstate 87 with Interstate 287 in a new configuration
and two new higher-speed E-ZPass lanes. The project was aimed
at easing congestion in the Tappan Zee Bridge corridor and
shortening commutes for motorists in Rockland County and points
north to Westchester County.
The project included:
- Widened connector roadways to and from I-87 and I-287.
- An additional auxiliary lane north and southbound to
ease traffic flow between the Tappan Zee Bridge toll station
and Interchange 8.
- New collector distributor roads to eliminate weaving
with the interchange.
- New higher speed E-ZPass lanes to improve traffic flow
through the Tappan Zee Bridge toll plaza.
Because of its location in one of the most congested corridors
in New York State - more than 135,000 vehicles cross the Tappan
Zee Bridge daily - no long-term road closures were allowed
and the same number of lanes was maintained during peak travel
periods throughout the project. A complex, staged construction
and traffic management plan was set up to assure maximum safety
and to minimize inconvenience to motorists.
Lane restrictions were limited to off-peak hours and lane
closures were not permitted during commuter or holiday travel
times. In addition, the authority's construction inspectors
monitored operations onsite, along with traffic supervisors,
engineers and construction experts.
Up to 250 workers per day worked to build 15 new lane mi.
and rebuild 19.6 lane mi. using 28,000 cu. meters of concrete
and 225,000 metric tons of asphalt. Four new bridges were
constructed, three bridges were rebuilt and four were replaced.
Three new noise barriers and 21 retaining walls were constructed.
Rock blasting on the project was more than the authority conducted
for all its construction jobs in a year.
The project featured several innovations. For example, the
250-ft.-long Broadway Bridge in Tarrytown is one of the longest
precast composite bridges ever built in the United States.
Delivered on a "train" of tractor trailers, the
huge panels were lifted into place by two giant cranes at
night.
At another location on the project, high-strength steel was
used on a 272-ft. bridge, the longest simple-span plate-girder
bridge in New York.
Most of the project's 21 retaining walls were built with
Doublewal retaining systems, saving more than $7.5 million
in construction costs and efficiently securing soil and rock
adjacent to the widened roadway. The highest wall measured
50 ft. and the longest, at 1,914 ft., is the longest Doublewal
ever built.
The project team also had to add a lane that would cut through
the mile-long Tallyrand Swamp, a marshy area where normal
embankment materials likely would sink. The design team proposed
using a lighter-weight expanded polystyrene fill that is being
used extensively in Europe but is relatively new to road construction
in the United States.
Back
to list >>
|