|
Section 2 of City Water Tunnel No. 3
Rank #1
Cost: $750 million
Digging began in October for the Manhattan leg of City Tunnel
No.3, considered the largest capital construction project
in New York history.
Located 550 ft. under the streets of Manhattan, the tunnel
is all about delivery safe drinking water to city residents.
Its sophisticated control system, the placement of its valves
in special chambers and the depth of its excavation represent
state-of-the-art technology.
The tunnel originates from 30th Street on the west side of
Manhattan and will run downtown to the Holland Tunnel. A second
section will loop north from that point up the west side to
Lincoln Center.
This 8.5-mi. section of the tunnel will be activated by 2011
at a cost of $750 million, according to Commissioner Christopher
O. Ward of the New York City Department of Environmental Protection.
Planning for City Tunnel No. 3 began in the early 1960s and
actual construction commenced in 1970. As part of a four-stage
tunnel project, tunnel No. 3 is expected to be completed by
2020 at a total cost of $5.5 billion to $6 billion, according
to the DEP.
At conclusion, the tunnel will be more than 60 mi. in length.
Stage 1 - which is already delivering drinking water - was
completed in 1998 and is a 24-ft. diameter concrete-lined
pressure tunnel that steps down in diameter to 20 ft. It runs
13 mi. from the Hillview Reservoir in Westchester, through
the Bronx, northern Manhattan and Queens.
The first section of Stage 2 - the Brooklyn-Queens section
running through Red Hook, Brooklyn, to Woodside and Astoria,
Queens - is complete and will be activated in 2007.
Construction of stages 2, 3 and 4 has been accelerated by
a tunnel boring machine known as "the mole," which
has been lowered in sections and assembled at the bottom of
the shaft. The TBM has chipped off sections of bedrock through
the continuous rotation of a series of steel cutters mounted
on a large-diameter, full-circular, welded steel cutter head.
The TBM is expected to allow tunnel workers to excavate at
an average of 50 ft. per day at a diameter of 23 ft. - more
than twice the rate possible through drilling and blasting
methods. Because the TBM bores into the rock, there is less
damage at the point of excavation and no noise at the surface
to disturb surrounding communities.
City Tunnel No.3 is 800 ft. underground at its deepest and
400 ft. at its shallowest point. While No. 3 will not replace
tunnels No. 1 and No. 2, it will enhance and improve the adequacy
and dependability of the entire water supply system and improve
service and pressure to outlying areas of the city.
The operation of No. 3 will also allow for the inspection
of Nos.1 and 2 for the first time since they were put into
service in 1917 and 1936, respectively, according to the DEP.
When completed, tunnel No. 3 it will include four large underground
valve chambers, numerous riser shafts with riser valve and
distribution chambers and surface access facilities.
Back
to list >>
|