|
Best of 2005 Awards
Griffiss Landfills
Award of Merit: Environmental
A $21.5 million project to cap landfills at the former Griffiss
U.S. Air Force Base in Rome, N.Y., has sealed off tons of
military hazardous waste.
Awarded by the U.S. Army Corps of Engineers as part of the
federal base closure program, the project to cover landfills
over 66 acres began in 2002 and will be substantially complete
this year.
The Best of 2005 jury was most impressed by the project team's
commitment to use local contractors and workers. New Jersey-based
Conti Environment & Infrastructure started with in-house
staff but transitioned rapidly to a regional workforce, said
Rich Hamlin, site superintendent and project manager.
By the second half of the project, the technical staff, craft
workers, and management were about 90 percent local, exceeding
the federal Base Realignment and Closure Commission's 70 percent
standard.
"Unemployment is very high in that area," one juror
said. "They used displaced workers. That's an achievement."
"Given the kind of work they're doing - they're wearing
hazmat suits - it's fairly significant [that they found local
expertise]," another juror added.
Landfill 1 was the most complex to cap, requiring a groundwater
leachate system. Landfill 2-3 had an asbestos disposal cell,
Landfill 5 was a heavily wooded four-acre site, and Landfill
7 spread across 11 acres.
The 22-acre Landfill 1 was the largest sector and entailed
the most extensive design, engineering, and remediation work.
Crews cleared all vegetation from the partially wooded site,
then made earthwork cuts and fills to the meet the state-mandated
slope range of 2 to 33 percent.
The cap consists of several layers to control movement of
moisture and gas. The first is a geocomposite gas venting
layer made of plastic mesh, which helps to control and direct
methane and other emissions from the landfill. The system
moves those emissions toward a series of PVC pipes sunk 7
ft. into the ground, surrounded by stone and extending upward
through higher layers and finally curving in a "candy
cane" shape above ground.
The next layer is a 40-mg plastic barrier membrane that prevents
moisture or gas from reaching the surface. Above that layer
is a geocomposite plastic mesh that controls the speed of
surface stormwater flowing over the barrier membrane. Gas
monitoring probes line the perimeter.
The cap is finished off by another 12 in. of soil, 6 in.
of topsoil, and landscaping. A 1,350-lin.-ft., 18- to 22-ft.-deep
leachate trench and a 2,400-sq.-ft. leachate treatment system
collects and removes contaminated groundwater.
Hamlin said the least routine part of the job was wetlands
restoration, in which crews collected and consolidated landfill
debris on an acre of the wetlands, reconstructed the natural
topography with heavily loaded peat, spread a special grass
seed mix, and planted native vegetation.
Key Players
Developer: U.S. Army
Corps of Engineers
General Contractor: Conti
Environment and Infrastructure
Design Engineer: EA
Engineering
Geosynthetic Installation:
Chenango Contracting
Surveying: LaFave,
White, & McGivern
Common Fill-Barrier Protection-Topsoil:
Harvey Construction
Seed-Mulch: Miller's
Landscaping
|