|
Best of 2005 Awards
Croton Dam Spillway Bridge
Award of Merit: Bridges
The bridge soars over Croton Gorge, spanning 200 ft. as part
of the road that crosses the top of the Croton Dam, which
at one time was the world's second-largest stone masonry structure
and remains a landmark and engineering marvel.
But the spillway bridge, built in 1975 to replace an original
structure erected in 1905, was slowly falling apart. Its design
and the lack of anchor bolts or other restraints to upward
movement contributed to severe displacement of the arch bases.
That displacement, combined with the concentration of the
bridge's load at the center of the arch, also led to overstressing
of the arch ribs.
The New York City Department of Environmental Protection
decided to replace the 1975 structure and ensure that the
new bridge would have a much longer lifespan. Though located
in Cortlandt, N.Y., in northern Westchester County, New York
City owns the site, which is part of its vast municipal water
system.
The project team - led by New York-based Hardesty & Hanover
as structural engineer and Kiewit Constructors of Omaha, Neb.,
as general contractor - had to complete the job on a tight
schedule. It also had to address community concerns over the
poorly detailed aesthetics of the 1975 steel open-spandrel
arch bridge.
With a design schedule of only three months, the team quickly
decided that rather than replicate the original 1905 span,
it would incorporate modern materials and approaches into
a structure sensitive to the historic context. The team chose
spandrel columns that recreate the fundamental appearance
of the original bridge while uniformly distributing deckloads
to prevent displacement of the arch bases.
At a detail level, the railing, which was fabricated from
steel castings and tubular steel, mirrors the spherical elements
of the 1905 railing on a smaller scale. Such attention to
aesthetics helped the resulting design to gain quick approval
from the New York State Historic Preservation Office and the
New York City Art Commission, winning commendations from both.
The team was able to expedite construction using an innovative
erection scheme that leveraged the old bridge. The project
was "actually a deconstruction-reconstruction in kind,"
said one juror impressed with the approach.
The team stabilized the old bridge by installing anchor beams
in its arch bases and removing its deck. The team then used
that structure to support the new bridge as construction proceeded.
The team installed new ribs to bear on the granite skewbacks
on an alignment that stretched farther than the arches of
the 1975 span - and that actually replicates the seating of
the 1905 bridge. This allowed the team to leave the 1975 arches
in place while installing the ribs.
The old arches, in turn, served as support for the installation
of new arch segments. The new arches then served as a support
for the team to disassemble the old arches. The new bridge
still uses the original foundation, including the historic
dam and masonry abutments.
The erection scheme also allowed crews to access the tricky
worksite via the old structure. Temporary beams slung below
the old arches supported a work platform and protective shield.
These loads then transferred to the new arch ribs upon their
installation, allowing the work platform and shield to remain
in place throughout construction.
To ensure the structure's longevity in the constant mist
rising from the spillway, High Steel Structures, a steel fabricator
based in Lancaster, Pa., used three coating processes on 250
tons of steel. It put the interiors of tubes that were used
as bracing elements through hot-dip galvanizing. It painted
the insides of sealed welded boxes to avoid potential warping
associated with the galvanizing. And it thermally sprayed
the exposed exteriors and other visible components with zinc-aluminum
metalizing.
The $4.6 million project finished on time in May.
Key Players
Owner: New York City
Department of Environmental Protection
General Contractor: Kiewit
Constructors
Engineer: Hardesty
& Hanover
Owner's Representative: Zubatkin
Associates
Steel Detailer: Tensor
Engineering
Steel Fabricator: High
Steel Structures
Tie Bags-Rock Bolts-Rock Anchors:
CTC Drilling & Blasting
Expansion Joints: Kinedyne
Corp.
|