|
Best of 2005 Awards
Brooklyn-Queens Expressway Rehabilitation
- 25th Ave. to Broadway
Project of the Year: Highway and Roadway
The
New York State Department of Transportation had serious concerns
about a 1.6-mi. stretch of the Brooklyn-Queens Expressway
in Queens.
The roadway from 25th Avenue to Broadway, built 50 years
ago, had narrow lanes, no shoulder, poor drainage, unsafe
curves, and substandard vertical and horizontal sight distances.
At the same time, it served as Interstate 278 - one of the
nation's busiest traffic zones with a volume of about 140,000
vehicles per day.
Those conditions sparked a $295 million, five-year-long reconstruction
completed in May.
"One of the most complex projects ever executed in the
city," said one Best of 2005 judge.
On any other highway, a widening, straightening, and drainage
improvement project might be a straightforward proposition.
Here, it was a planning feat.
"Every 100 yd. on one of these jobs is a project unto
itself," a juror said.
Not only did the project require maintaining the highway's
traffic flow, but crews had to work within a densely developed
and populated neighborhood, encountering work areas as small
as 12 ft. beside the highway. In addition, the highway straddles
a CSX railroad line, with 3,000 ft. of rail running through
the project area, forcing the team to contend with rail structures
such as a bridge over the highway; a bridge for the line to
pass under Broadway that the team refurbished; and three bridges
over local streets, all of which the team demolished and replaced.
The effort to rebuild the highway was dependent in large
part on freeing up space by moving the rail line, said Peter
Franco, project manager for Slattery Skanska of Whitestone,
N.Y., the general contractor. The bulk of the early work involved
replacing the rail line's three existing bridges - over the
highway, 34th Avenue, and 35th Avenue - with one nine-span
structure, which was installed in two stages and had eight,
10-ft.-diameter drilled shafts for supports.
The task included lowering the two avenues and 69th Street
by up to 10 ft., while also reburying existing utilities such
as 48-in. and 72-in. water mains, 12-in. and 20-in. gas mains,
sewer lines, electrical ducts, and communications lines. After
that effort finished in August 2002, the crews rebuilt a rail
bridge over Northern Boulevard, installing a three-span structure
with three trusses.
At that point, there was finally room to straighten out and
widen the highway, even though the project team still had
to contend with a tight work area, difficult soil conditions,
and proximity to neighborhoods. For instance, in order to
reduce noise and vibrations, the design called for drilled
shafts rather than driven piles along 93,000 lin. ft. of foundations,
including work around bridges and retaining walls. The task
was more difficult because of the prevalence of 10-ft. boulders
buried in the soil.
One of the tighter spaces around the Northern Boulevard Bridge
required crews to use 500-ton Liebherr cranes, capable of
extending heavy loads out to the work area. On other occasions,
in order to erect retaining walls for bridges, crews had to
build access ramps to get drills onto the embankments.
In all, the project involved 3.5 mi. of retaining walls,
more than 38,000 lin. ft. of soldier piling, and 18 temporary
ramps.
When crews finally got to the highway itself, they had to
demolish and rebuild 13 bridges in similarly tight spaces.
To support construction of the bridge sections, engineers
eschewed traditional framing because of the space conditions
and instead used a geosynthetic reinforced earthwall system,
which consists of layers of sand set between sheets of geosynthetic
fabric and L-shaped wire baskets holding the sand inside each
layer. The team built 40 of these temporary walls.
Dhiaa Shubber, program manager for Parsons Brinckerhoff,
the construction manager, said one of the keys to making the
project flow more smoothly was having constant meetings with
local community boards, groups, and government agencies.
The project overall encompassed four stages and 40 phases,
with most work taking place during off-peak hours. The team
also used cattle chutes to redirect vehicles, with up to five
chutes in operation at once.
Key Players
Owner: New York State
Department of Transportation Region 11
Construction Manager: Parsons
Brinckerhoff
Engineer: Joint venture
of URS Corp. and Goodkind & O'Dea
General Contractor:
Slattery Skanska
Design Team: Mark K.
Morrison Associates; Urbitran Associates; Muñoz Engineering;
Konheim & Ketcham; Edwards and Kelcey
Project Team: Koch
Skanska; Underpinning & Foundation Skanska; Trevi Icos;
ADF Group; Perini Corp.; Ferrara Bros.; United States Rebar;
Welsbach Electric; Precast Systems; St. Lawrence Cement;
Master Builders; CFS Steel; Binghamton Precast & Supply;
Carabie Corp.; Peduto Construction; Tricon Enterprises
|