|
Best of 2005 Awards
Third Avenue Bridge
Project of the Year: Bridges
Though
not as famed as the Brooklyn Bridge, the Third Avenue Bridge
over the Harlem River has long been a vital part of New York's
road network, carrying 80,000 vehicles a day from the Bronx
to Manhattan. But the deteriorating structure that first opened
in 1898 had clearly seen better days.
Those conditions laid the groundwork to totally replace the
bridge, a project that reached substantial completion this
year. It garnered not only top honors in its category from
the Best of 2005 jury but also made the panel's short list
for the overall project of the year.
"It was an incredibly complex project," one judge
said.
The project called for intimate involvement from numerous
government agencies; the need to keep road and river traffic
flowing as work proceeded; and the development and execution
of an intricate design for a new swing-span bridge that will
meet the city's traffic needs for decades to come.
"The contractors had incredible permitting issues on
gaining access to the river bottom," one judge said.
"The city really constrained them, because it wanted
to make sure they did this job right. There are several other
bridges they plan to replace upriver."
The design team, led by Hardesty & Hanover of New York,
planned a bridge that maintains the historic aesthetic of
its four-lane predecessor while enhancing traffic flow and
safety. Instead of the old layout of a pair of side-by-side,
two-lane spans, the new five-lane alignment more smoothly
manages traffic congestion. It also cuts down on lane-changing
difficulties that had contributed to a high accident rate
on the old span.
The four-year, $128 million project also involved the replacement
of approach ramps, mechanical and electrical systems, and
the bridge's control house, as well as rehabilitation of the
rotating gears to work with the new swing span. Led by New
York-based Parsons Brinckerhoff as construction manager and
resident engineer and the New York affiliate of Turkey-based
KiSKA Construction as general contractor, the project team
working for the New York City Department of Transportation
included specialists such as engineers, naval architects,
structural monitors, safety inspectors, and community outreach
officers to assist the motoring public.
Although the original plans called for the bridge to be
completely closed for six months, the department instead decided
to have the contractors keep two lanes of traffic and one
sidewalk open throughout, requiring the installation of a
temporary span running parallel to the old structure. The
300-ft.-long temporary steel plate span allowed the team to
limit full traffic closure to just two weekends. The project
also had to meet a U.S. Coast Guard requirement to have at
least one navigational channel open at all times.
The entire bridge, including approaches, is 3,500 ft. long,
with 17 steel girder approach spans leading to the 350-ft.
long, 6-million-lb., steel through-truss swing span. Forged
at a mill in Alabama and shipped to New York on an ocean-tow
barge, the project team floated the span into place on the
Harlem River in October 2004, with the first two lanes of
traffic opening two months later.
All five lanes opened by February, with intermittent closures
throughout the year as work continued. Final touches, including
new streetlights, work on an off-ramp, and final mechanical
and electrical tasks, are scheduled to wrap up in early winter.
The new bridge will operate more efficiently because it
uses a center pivot bearing instead of the rim-bearing design
it supplanted - a change that also made the replacement span
easier to install. It features a 65-ft.-long, 100-ton steel
box girder that transfers the span's entire weight to the
center pivot, which is a spherical roller thrust bearing that
is 5 ft. tall and nearly 10 ft. in diameter.
The bearing is designed to handle the 6-million-lb. vertical
load and a 1-million-lb. horizontal seismic load. The truss
connects to the transfer girder via more than 400 high-strength
1-in. bolts.
"It's unbelievable how complicated the construction
is of the systems required to move the spans," one judge
said. <<
Key Players
Owner/Client: New York
City Department of Transportation
Design Team: Hardesty
& Hanover; Philip Habib Associates; B. Thayer Associates;
Gandhi Engineering
General Contractor: KiSKA
Construction
Construction Manager: Parsons
Brinckerhoff
Steel Fabricator: G&G
Steel
Steel Detailer: Amec
Zizka
Asphalt: Cofire Paving
Mechanical: E-Mech
Contracting
Plumbing: Empire State
Piping
Stone Installation: Graniteworks
Rebar Installation: Island
Reinforcing
Utilities: Peduto Construction
Electrical: D.L. Blaine
Corp.
Pile Installation: Underpinning
& Foundation
Rebar Installation: United
States Rebar
Submarine Cable Installation:
UWL Co.
Engineering: Haley
& Aldrich; Urbantech
Surveying: Loftus
Community Outreach:
Zetlin Strategic Communications
|