|
Award
of Merit - Transit
Westport Station Pedestrian Underpass
Sometimes great things come in small packages. That's true
at the Westport Station pedestrian underpass, a 75-ft.-long,
14- by 14-ft. tunnel that employed cutting-edge tunneling
technologies never used before anywhere in the country.
The tunnel's $2.5 million price tag looks minuscule next
to the $100 million price tags associated with urban infrastructure
projects, but the client - the Connecticut Department of Transportation
- got a lot of bang for its buck.
The project team had to design and construct an upgrade
compliant with the Americans with Disabilities Act for the
Westport Commuter Rail Station. That upgrade also could not
take any of the four active Metro-North Railroad tracks that
run overhead out of service at any time.
"It was executed under a working railroad," said
one juror. "That's not easy."
Several factors set the table for the design team. First,
hybrid soils - which ranged from a mix of relatively weak
and soft deposits on one side of the tracks to hard bedrock
on the other - made conventional tunneling impractical. Another
project demand was avoiding a complicated system with deep
access stairs and elevator connections. Had the team employed
existing soil stabilization techniques during the short nighttime
windows when trains were not active, the project schedule
could have dragged out several years. Rerouting trains via
a temporary bypass wasn't a realistic option, either. The
design team had to think outside the box.
Its solution called for the tunnel to be jacked under the
tracks, with the roof of the tunnel passing just 2 ft. under
the ties supporting rails that carry hundreds of Metro North
and Amtrak trains a day. The jacked tunnel used a grillage,
a technique never attempted in North America. The grillage
consisted of a series of preinstalled interconnected orthogonal
beams running parallel and perpendicular to the rail tracks.
The design spaced the main beams at approximately 7-ft. centers.
The design called for the project team to progressively
transfer the loads of the tracks from the ties, which rest
on the ground, to the grillage and then to the roof of the
advancing tunnel. The design also ensured the grillage could
safely support the tracks in all situations, including ground
failure in the area ahead of the advancing tunnel.
The team installed small steel box beams parallel to the
track along the length of the tunnel. Construction crews went
in at night to excavate small 2-ft.-deep, 12-in.-wide trenches
and then installed the 90-ft. long steel beams that, once
connected with the box beams, created the steel framework
of the grillage.
At the end of the project when the tunnel was in place,
the crews placed and compacted ballast between the underside
of the ties and the top of the tunnel roof. It then removed
the grillage beams, finally transferring the load of the tracks
to the top of the tunnel.
The tunnel itself was cast in a joint-free box pushed under
the grillage at a rate of 2 to 3 ft. per day. The entire tunnel
project took about six months, but it took less than 30 days
to jack the tunnel through the ground despite the need to
navigate a large boulder encountered in softer soils under
the tracks. The project team halted tunnel installation for
several days to drill, split, and remove the boulder.
The significance of the Westport project lies far beyond
the creation of a pedestrian underpass at a busy station.
The conditions required creative thinking, and that process
showcased a new technology available to engineers and contractors.
In its submission, Boston-based Hatch Mott McDonald noted
that since the Westport project, the company has fielded requests
to use the tunnel-jacking technique in various other locations.
|