|
Project
of the Year - Environmental
Springfield Gardens Industrial Park
Plaudits for the Springfield Gardens Industrial Park project
came because the end product was a creative solution to a
decades-long drainage problem that had wreaked havoc on a
busy network of intersecting streets in Queens. But they also
came because of the attention the project team gave to minimizing
construction impact in the heavily trafficked area.
It was clear that the Springfield Gardens area of Queens
needed more than a storm drainage system. It needed a full
infrastructure facelift. The poor state of curbs, sidewalks,
and roadways had exacerbated the drainage problem, while equally
deteriorated water mains had affected the quality and reliability
of the area's water.
The deteriorated state of the area led the New York City
Department of Environmental Protection to adopt a big-picture
solution that included installation of a new storm-sewer system
and the creation of two acres of tidal wetlands. It also commissioned
water-main replacement and full street reconstruction.
"It's an environmental project that provides extraordinary
relief to the residents in the area," said one juror.
The $31 million project also earned kudos from the jurors
because of its attention to the needs of the community during
the construction period. The industrial park included approximately
50 blocks of warehouses, businesses, and food operations,
many to service neighboring John F. Kennedy International
Airport.
Trying to minimize the neighborhood impact was harder because
the required level of street disruption was significant. The
job called for deep excavation, sheeting, and dewatering in
order to install and construct a sewer network of trunk lines
and piping. In the end, the project team laid more than 19,000
lin. ft. of new ductile iron-restrained joint water mains
as well as over 9,000 lin. ft. of new sanitary sewers.
To keep the area open for business while carrying out the
street program, the project team implemented an extensive
community outreach effort that included compiling a list of
every company doing business in the area. The team shaped
construction sequencing around the basic premise that business
owners would have access to their operations at all times.
"We were doing little hopscotches all over the place
trying to keep everyone in business," said Tom Donnelly,
vice president of New York-based Daniel Frankfurt, PC, which
was the resident engineer for the project.
A main culprit for the drainage problem was the area's high
water table, which is only 5 to 6 ft. below the surface. In
order to complete the in-ground work, the contractor, EIC
Associates, had to install deep well pumps that ran around
the clock and kept the construction area dry while crews were
laying the pipes.
To provide a long-term solution to the drainage problem,
however, the team had to find a place for the water to go
during wet periods. During rainy spells, it was common to
have a 3-ft. deep pool of water settling in the area, because
it had no outlet.
That's where the project design called for creating tidal
wetlands out of an upland area. The project team dug a stream
bed from the industrial park to the tidal area, providing
the long-absent capacity for stormwater runoff - giving the
water somewhere to go. The jury cited the ability to accommodate
such diverse goals as a prime reason for honoring the project.
"They didn't have as much space to work with when putting
in these improvements," a judge said. "This is an
extraordinary project."
|