|
Award
of Merit - Higher Education
Center for Environmental Sciences
and Technology Management at SUNY Albany
Creativity within strict constraints was the signature achievement
for the three-phase Center for Environmental Sciences and
Technology Management at the State University of New York
at Albany.
The $97 million CESTM project involved the design and construction
of 368,000 sq. ft. of facilities, including 73,000 sq. ft.
of class-1000 clean-room space. The innovative structure housing
laboratories, offices, conference rooms, and electronic communications
is the first university-based building of its kind - and now
serves as a home for the nanoelectronic technology community.
In the three-year construction window, the most the most
challenging phase by far was the final property, the $50 million
Nanofab 300 North. The university intends for that unique
facility to catalyze the entire nanotechnology industry -
from concept to market introduction support. Nanofab is also
an integral part of other state-funded research hubs in Buffalo,
Rochester, Syracuse, and Long Island.
But the end users of the facility are not the only ones
utilizing high technology and creativity to deliver their
product. Building the new center took that same focus on technologically
advanced methods mixed with the specialty of higher education
construction. It also helped the project team, led by Welliver
McGuire Inc. of Elvira, N.Y., the construction manager, overcome
various obstacles.
"Despite the terrible site conditions, high water table,
and state budget delays, they got the job done on time,"
said one jury member.
The first challenge of Nanofab, which broke ground in late
2002, was site access. The project bordered a busy thoroughfare
on one side and on the other side faced buildings and a hill
that was later removed. In addition, a major gas transmission
line ran through the property.
Then there were the sandy soil conditions. The water table
on the construction site was only a few feet below grade,
requiring Welliver to install and manage a dewatering system.
The sandy soils made installation of piles critical to the
building's functionality and safety. The 1,400 auger cast
piles - installed to a depth of 70 ft. to 80 ft. - prevented
structural failure in case of liquefaction, a dangerous phenomenon
resulting from a seismic event in sandy soils, which turns
underground dirt into liquid and can destroy building foundations.
The team also had to dig deep foundations to prevent ground
vibration from affecting machinery in the clean rooms. Furthermore,
the team had to complete all of that groundwork without disturbing
expensive, highly sensitive tools housed in the earlier phases
of the project.
The awards jury recognized that sensitive mix. One member
cited "the complexity of use for this building and the
challenge of site conditions in constructing it."
Both public and private funding arrived slowly, making project
management even more difficult. For instance, it delayed the
pile installation work until winter 2003. That delay also
forced the team to pour structural concrete during the winter,
and led to additional work, such as installation of an all-encapsulating
waterproof membrane system to protect against water intrusion.
|