|
Award
of Merit: Bridges
Riverside Drive Bridge over West
96th Street
The Riverside Drive Bridge over West 96th Street is a 1,110-sq.-ft.
three-span steel structure that carries six lanes of vehicular
traffic and two pedestrian sidewalks. But it needed a $4.7
million facelift to rehabilitate corroded structural steel
and restore the bridge to its original beauty.
The judges called the project a success. "It's very
hard to build an attractive overpass, but they've done it
here," one juror said.
Originally built in 1920, the roadway portion of the bridge
consists of reinforced lightweight concrete deck. Columns
and struts of the exterior rigid frames are enclosed in massive
architectural stone masonry work. The bridge, in a park setting
within a residential neighborhood, is aligned northeast, crossing
on a skew of 69 degrees.
While the rigid-frame bridge underwent work in 1996 to repair
the lightweight riveted structural steel components, a lack
of funding left several elements untouched, including granite
stone enclosed components of fascia girders, sidewalk portions
of steel pan plate, railings and their bases, and sidewalk
approach pavements. Those tasks became part of the job led
by Gandhi Engineering Inc., the New York-based engineer and
prime consultant.
Among the unique elements of the project was working with
the mix of granite stone masonry and structural steel. The
granite stone masonry hid the corroded load-carrying steel
members from view, making them inaccessible for inspection.
One of the major construction tasks involved removing that
granite stone masonry and the balustrade enclosures along
the first and third spans in order to uncover encased corroded
steel.
As the project team moved forward with work on the masonry,
it kept uncovering more defective steel members, thereby increasing
the scope of the work progressively. The rigid-frame spans
measure 21 ft., 70 ft., and 21 ft. for a total length of 113
ft. Nine rigid frames line the bridge, spaced approximately
13 ft. center to center.
In completing this rehabilitative portion of the job, the
project team had to erect new structural steel members and
then had to reinstall the architectural stone masonry.
The job entailed other significant tasks, including installing
new lightweight reinforced sidewalk concrete, new steel-faced
concrete curbs, new tie-down steel anchor rods, new reinforced-concrete
barriers on the two sidewalks, and new bridge railings. Lead
paint removal and electrical work capped the extensive repair
operation.
|