|
Award
of Merit - Highway
Reconstruction of the Long Island
Expressway
Twenty-seven bridges along 7 mi. of the Long Island Expressway
between Van Dam Street and the Grand Central Parkway needed
reconstruction and rehabilitation. The job seemed even more
daunting, since the LIE is one the most heavily traveled highways
in the nation.
The New York State Department of Transportation's resulting
$170 million program also entailed new safety concrete barrier
medians, wider shoulder areas, improved super-elevation, better
signage and lighting, and an Intelligent Transportation System
guiding motorists.
At the outset, the project team faced structural, geometric,
and operational deficiencies on walls, bridges, and pavement
all along the narrow corridor. Such constraints required extensive
maintenance and efforts to protect motorists during all project
phases. Adding to the challenge was a densely populated community
around the work area.
"This is not your standard project because there were
no separate work zones," one judge said.
But the biggest obstacle was that transportation officials
wanted three lanes of traffic open in both directions, requiring
the project team, led by LiRo Engineers as construction manager,
to stagger traffic volume.
The project's sheer complexity encouraged the team to operate
in multiple stages. The schedule included more than 3,500
activities and seven B-clock tasks that had associated incentive-disincentive
payments. The tasks included repairing substructures, pile
driving, extensive painting, and replacing piers, abutments,
and decks. The engineering team also designed a multilevel
pre-cast concrete post-and-panel retaining wall system.
The bridge reconstruction efforts were extensive, including
widening the Queens Boulevard Bridge and replacing superstructures
and parts of substructures for six bridges over the highway.
Perhaps the most complex task was replacement of the deck
and structural steel on the 58th Street Bridge. The work involved
installation of 16 Inverset panels, each 82 ft. long. Since
this portion required some traffic shut down, transportation
officials granted one weekend for the work. The team developed
an hour-by hour schedule detailing every construction task,
along with written contingency plans.
"You had to build the service roads [and] build on
the main line, all with only four weekend days of service
outage," said one judge. "Logistics management in
that environment is a big challenge."
|