|
Project
of the Year
FDR Drive Outboard Detour Roadway
By Tom Stabile
A
mile and a quarter of detour roadway is seldom the stuff of
great acclaim. But the FDR Drive Outboard Detour Roadway left
the awards jury marveling at everything from innovative engineering
to smooth execution.
"The ingenuity of the FDR Drive project is what gets
the kid in all of us excited," one judge said.
The temporary detour opened in May after 18 months of construction
as the anchor of a $136 million project to rebuild the deteriorating
highway. The signature of the $40 million detour portion,
which runs from 51st to 64th streets, is the half-mile "outboard"
built over water from 53rd to 60th streets.
"The whole concept of building a temporary bypass out
in the East River and then taking it back down again afterwards
is pretty unique," said David Vosseller, marine project
manager for Weeks Marine of Cranford, N.J., which built the
roadway in a joint venture with Slattery Skanska of Whitestone,
N.Y.
The detour carries two lanes of northbound traffic, allowing
the project team to shut down one section of the permanent
roadway at a time for major demolition and reconstruction.
Among rebuilding tasks ongoing through 2007 are replacement
of bridge and viaduct superstructures, rehabilitation of the
highway roof structure and retaining walls, and retrofitting
for seismic shoring, lighting, signs, and drainage. The highway,
also known as the East River Drive, funnels 150,000 vehicles
daily along Manhattan's east side, and is a critical artery
linking bridges and tunnels up and down the island.
Observers from many vantage points, including the awards
jury, have said none of that work would have occurred without
the detour. That's because there was little appetite among
city and state leaders for the more standard reconstruction
approach - shutting down lanes, stomaching traffic backups,
and likely requiring most of the work to take place at night.
The jury noted how residents in the upscale East Side neighborhoods
near the proposed work pushed hard to prevent a scenario that
would have flooded local streets with traffic.
"It's also in a league of its own for the innovation
and the thinking and the cooperation they had to elicit from
the United Nations, from the Coast Guard, from the neighbors,"
a juror said. "Complex to execute technically without
question, but also because of all of the work they had to
do beforehand."
That backdrop explains why the New York State Department
of Transportation sought other solutions, eventually turning
to New York-based Daniel Frankfurt Engineers & Architects.
Its president, Neil Lucey, said a highlight of the outboard
detour approach is eliminating nearly all of the nighttime
work.
"You could say under a conventional plan you'd have
20 more times nighttime work," Lucey said.
More Bridge Than Highway
The roadway's basic design impressed the jury. "From
a technical standpoint, it's innovative," one juror said.
"It's head and shoulders above the rest."
The 22-pier bent detour bridge section sits atop 64 steel
pipe caissons socketed into the river bedrock. Those hold
the steel superstructure supporting precast concrete panel
slabs, a layer of asphalt, and a corrugated metal panel roof
to shield noise and light.
The idea of a detour over water grew from a floating highway
concept state transportation authorities had considered, Lucey
said. His firm teamed with three other New York-based consultants
- Earth Tech/TAMS, DMJM Harris, and Sam Schwartz Co. - to
design an over-water detour with a protective fender system
in the busy East River shipping channel.
"What made it possible was that the transition back
to the land was there," Lucey said. "At the north
end, it's the old 60th Street heliport, and at the south end,
at about 53rd Street, there's a little disabled vehicle turnout."
That was enough. The team conjured up a temporary structure
- more bridge than highway, Lucey said - that could keep the
road's existing design speed, stay within the planned budget,
gain necessary permits from agencies like the U.S. Coast Guard,
and handle wind, currents, and ice. It planned a structure
10 to 14 ft. above mean sea level - higher than the permanent
northbound lanes - and an alignment addressing all of those
factors, as well as features such as subway tunnels below
at 53rd, 60th and 63rd streets, the Queensboro Bridge above
at 59th Street, and critical entry and exit ramps.
The study and design phases ran from 1998 to 2001, said
Neil Porto, senior project manager for Daniel Frankfurt. Construction
started in November 2002, with the joint-venture contractor
splitting most over-water work to Weeks and most land work
to Slattery.
Slippery Challenges
The team encountered the choppy East River early on. It
has five to seven feet of tide variation and flows at 3.5
to 4.0 knots - close to 5 m.p.h. - which is a significant
speed for marine work, Vosseller said. Sometimes those flows
were in one direction on the surface and another below.
But Weeks had ample water work experience and resources,
said Tom Bowers, engineer in charge and project manager for
the department of transportation. For the over-water portion,
Weeks met varying river conditions with one barge setup using
anchors on the north side and another using a jack-up system
that stabilizes against currents and waves on the southern
half. Meanwhile, having multiple setups allowed the team to
always be building at least two sections of the roadway.
"No one dreamed they would have two full barge setups
in the water, plus a barge system for the fenders," Bowers
said. "That saved a lot of time."
A major task for the barge crews was installing the caissons.
But before they could proceed, the team had to make sure it
didn't bore into the subway tunnels. Bowers said Slattery's
infrastructure expertise - and its ongoing contracts with
the Metropolitan Transit Authority in those same tunnels -
was a big help.
In addition to helping the team precisely locate the tunnels
to avoid damaging them with caisson boring, Slattery was able
to piggyback the drilling schedule onto an already planned
subway service outage for other work the company was overseeing
in the East River tunnels. That saved months of negotiating
with the MTA, Bowers said. The intricate work also helped
the team plan for some land-based portions where the temporary
roadway will place partial loads over the tunnel sections.
That planning set the table for one of the biggest technical
challenges - digging holes for the 54-in. diameter steel caissons.
Besides the fast current, the team had tough conditions at
the river bed, where there was little or no soil on top of
the bedrock, making it harder to drill. And there were other
complications, Vosseller said.
"Trying to install and develop the sockets was hard,
because the rock itself sloped on a 45 to 50 degree angle,"
he said. "We had to develop a method that was going to
prevent that drilling equipment from skittering down that
slope."
Despite the challenges, the Weeks team of divers, drillers,
and other crews completed about one caisson every 2.5 shifts,
working one shift a day. The procedure started with drilling
about 55 ft. into the bedrock - already 25 ft. under the surface
- and inserting a 90-in.-diameter casing as a slot for the
core barrel drill. From there, the team placed a 79-in. diameter
casing in the hole, and within that, developed a 74-in. diameter
socket down to the drilled bedrock. The team then placed the
54-in. caisson in that socket and filled the entire casing
with concrete up to the river bed. Above the bed, the caissons
are hollow up to the superstructure, and they have a steel
plate cap to connect with the superstructure.
On the portions of the fender and detour road installations
under the Queensboro Bridge, the team had to shorten the crane
booms in order to have enough headroom, Bowers added.
Decked and Fendered
Once caisson installation finished on a particular stretch,
the next phase of installing the steel superstructure would
begin. That framework consists of transverse steel-cap beams
and 100-ft. long longitudinal steel girders.
Waves of work crews would roll behind each completed stage,
so installation of the precast concrete deck followed as superstructure
work finished. Right behind the deck came asphalt surface
paving, followed by sound barrier panel installation. "It
took a lot of project coordination, a lot of scheduling,"
Bowers said.
In tandem with the detour are other features, such as an
elevated roadway serving as a temporary exit ramp for East
61st Street, and an entrance at 60th Street that rebuilt a
ramp to the old heliport. "We're maintaining all the
vital ramp connections," said Daniel Frankfurt's Porto.
Another technological highlight is the fender system out
in the river. Porto said DMJM Harris designed the system,
the first of its kind, to gently guide errant ships back into
the East River channel, and away from the detour road.
The $28 million system consists of a 10-ft.-diameter floating
fender beam "guardrail," in sections 250 ft. long,
connected by 13 floating barge-like "dolphins."
These 18-ft.-deep, 20-ft.-wide, and 20-ft.-long structures,
encased in metal with a hardened black plastic exterior, stay
in place amid changing currents and tides thanks to four rock
anchors, some running 120 ft. deep, tied to each one with
chains. Divers did a lot of the heavy anchoring work, Vosseller
said.
Quick Lifespan
For all of its innovation, the temporary roadway will have
a short existence. Built to last 10 years, its role is merely
to buy time for crews rehabilitating the permanent roadway,
particularly a stacked section where the northbound lanes
are above southbound ones. Work began on that portion in earnest
this year, with the installation of a demolition shield over
the old northbound lanes, to which crews have diverted traffic
heading south in order to begin work on the old southbound
lanes.
Porto said a major point of pride is how the detour portion
came together with almost no impact on the traveling public.
"It was only when the crossovers needed to be connected
that there was some weekend work during those times,"
he said.
Once the reconstruction work is done in 2007, however, the
detour will leave little mark after the team disassembles
it. Bowers said there are already plans for the sections to
journey south by barge, where they will meet a watery grave
- joining old New York City subway cars off the Atlantic coast
in an artificial reef.
|