|
Project
of the Year - Industrial
East River Repowering Project
The East River Repowering Project entailed plugging in an
additional 360 megawatts of power to stabilize steam rates
and to maintain reliability of energy production for steam
customers of Consolidated Edison, the major New York utility.
But completing the $235 million job also involved a big
constraint. The project called for the installation of two
dual-fuel combustion turbines, two heat-recovery steam generators,
a 5,000 GPM demineralization facility, and 80,000 sq. ft.
of process piping - all without increasing the size of the
station.
"The site logistics were a big challenge, especially
because it was close to the river," one jury member said.
The facility sits in a confined space in lower Manhattan
bounded by city streets on three sides and the FDR Drive on
the other. With virtually no lay-down area to work in, the
project team had to creatively manage the job without interrupting
power and steam distribution to customers.
Retrofitting new equipment into an existing structure wasn't
easy. "The real challenge was within the building, because
they had to strengthen and readapt part of the facility,"
added another awards panel member.
The schedulers, engineers, and supervisors closely coordinated
delivery and installation of materials and equipment to the
site. An early task was offloading equipment via barge from
the Hudson River. The team had to transport equipment to the
site and use two 650-ton cranes to lower the pieces into the
facility through construction openings in the roof and sidewall.
Due to the tight work site, the project team also decided
to prefabricate the heat-recovery steam generators and combustion
turbine components at the Marine Ocean Terminal in Bayonne,
N.J., only delivering them as needed.
But even those solutions required adjustments. The prefabricated
materials exceeded normal shipping weight and size limits,
requiring special planning for road logistics and off-loading
at the site.
The job also entailed construction of a new, onsite water
treatment plant employing a 9,000 GMP reverse-osmosis system
to produce pure water for steam generation. One juror cited
that element specifically, saying it contributed to "a
very complex project."
The project not only allows the station to increase production,
but also allows Con Edison to close its less-efficient Waterside
Generating Station on First Avenue. The station will reduce
overall emissions by up to 70 percent compared to the Waterside
Station.
|