|
Award
of Merit - Renovation
640 Fifth Avenue
The project team that renovated and redeveloped 640 Fifth
Ave. in Manhattan needed to turn an 18-story building into
a 21-story building without disrupting the office tenants
or retail customers inside it.
The $38.3 million project involved constructing a three-story
addition to the 267,000-sq.-ft. structure built in 1949 on
the west side of Fifth Avenue between 51st and 52nd streets.
The building now has 302,000 sq. ft. with standardized floor
plates and common rentable floors. Tenants occupied the first
eight floors throughout the project.
"It was a big job, well executed," said one judge.
The project also involved extensive renovations. The project
team stripped the existing exterior limestone façade
from the 18th floor down to the 10th floor, and built and
maintained a temporary protective roof for a full season.
The team also completely renovated the lobby and added floor-to-ceiling
windows, which provide views of St. Patrick's Cathedral and
the rooftop gardens of Rockefeller Center.
The team also replaced and relocated the building's mechanical
and electrical equipment in a phased sequence, while keeping
systems for the occupied floors operating.
The project team had its work cut out to not disrupt tenants
in the building or pedestrians on the busy surrounding sidewalks.
That added to the complexity during all phases of construction,
such as the steel structure erection, installation of the
glass curtain wall, construction of the temporary roof at
the 10th floor, reinforcement of steel columns, and replacement
of windows. One solution the team developed was eliminating
hoist delivery of materials to the upper floors. Instead,
the team used the tower crane on site for structural steel
erection.
Similarly, the team carefully managed elevator renovation.
It maintained the existing service while reconditioning the
cabs on four low-rise elevators by programming a different
sequence and focusing on one elevator at a time. For the renovation
and extension of the four high-rise elevators, the project
team demolished half of the existing elevator machine room
and brought two of the new shafts through it, while keeping
the other two operational for construction personnel. It repeated
the process in the remaining half of the elevator machine
room for the last two elevators.
Another aspect of the renovation involved installing new
cooling towers and a water tank. The project team erected
the new towers and tank above the existing ones, built the
new three-story addition around them, tied in the new equipment,
and then removed the old systems.
Crews erected the steel by cantilevering a Gantry tower
crane out from the existing base building at the 12th floor
on a steel platform. While the approach required the team
to reinforce the building in certain locations to support
the new load and crane, it also allowed full completion of
each floor as the steel went up.
The team also installed diagonal bracing, which transferred
the new load to the building's center core. This approach
- devised by the structural engineer - involved welding a
new steel plate at the flange to reinforce and strengthen
each structural steel column to carry the additional load
of the new upper floors.
"It was a total change in use with major building upgrades,"
said a judge.
|