|
Award
of Merit - Transit
1/9 Subway Ventilation Plants
Constructing two new vent plants for the 1 and 9 subway
line in Lower Manhattan echoed other jobs that took on massive
underground infrastructure improvements.
"These were extraordinary insertions in an environment
that was very difficult to work in," one judge said.
"They had to build that the same way they built the Big
Dig up in Boston."
The $59 million project involved replacing two fan plants
destroyed by the Sept. 11 terrorist attacks. Located north
of the World Trade Center site, the Park Place Fan Plant consists
of three 150 HP fans producing a total of 300,000 CFM. The
Albany Street Fan Plant, located south of the trade center
site, consists of two 200 HP fans and also produces 300,000
CFM.
A project of this scale usually takes four years to complete,
but the 1and 9 job took 22 months. Crews built the two plants
simultaneously, working extended hours, six days a week.
The project team could not begin work until after Jan. 1,
2002, because of a local requirement halting such work until
after the holiday season. New York City Transit granted the
project team one year to keep Albany Street closed, but the
project team reopened the street in 10 months.
The construction involved installing a sheeting bathtub
approximately 50 ft. deep by 200 ft. long at each site. Since
both plants are completely below the city streets and surrounded
by commercial and residential buildings, stability of the
existing subsurface was a concern. To address this, the team
used steel sheeting, bracing, roadway decking, and chemical
grouting to control the groundwater and soil.
The team had to safeguard streets, surrounding buildings,
and groundwater levels, while also monitoring water, sewer,
gas, steam, telecommunications, and electrical utility lines,
all which ran through the site's footprint. The team had to
ensure continued operation for all utilities during the entire
construction period. The team accomplished it by providing
temporary utility service outside the main cuts or by hanging
existing utilities from below the decking system.
"The project team really executed it well, to dig underneath
the infrastructure and create the environment they needed
to insert the steel," said one judge.
With 30 subcontractors on the job, the project required
detailed planning and scheduling to allow multiple trades
to work at the same time. The team coordinated with local
unions, subcontractors, and vendors to limit crews on site
to essential staffers.
A limited staging area also presented challenges. The team
staged deliveries to limit materials around the worksite.
It also engaged in meticulous planning to ensure workers had
the necessary materials to complete programmed tasks, while
keeping unnecessary material deliveries away.
The proximity to numerous residential buildings also limited
the loudest work activities to certain hours. Work impacting
subway service or vehicular traffic took place during night
and weekend hours. The project team also had to update New
York City Transit daily so that the agency could post bulletins
on its Web site to keep the public informed about upcoming
construction activities.
"I don't know how they ever did it," said one
judge.
|