|
Town of Halfmoon Water Treatment Facility
A new 2.0-mgd water treatment facility that opened in August
has provided a big boost to the Town of Halfmoon, N.Y., a
fast-growing residential and commercial hub about 300 miles
north of New York City.
The town, which had been purchasing water from a neighboring
community, decided to meet its long-term water supply needs
by building a new facility.
The project team responded with plans for a $10.3 million
facility using new treatment technology that promotes faster
sedimentation of water with highly variable turbidity-just
right for the chosen Hudson River source. The facility also
features a raw intake and pump system, five chemical feed
systems, on-site sludge and backwash disposal, and a water
storage facility.
First up, the project team had to select the water source
- from the Tomhannock Reservoir, the Mohawk River or the Hudson.
It weighed potential problems such as high mineral content
and inactive hazardous waste sites at the reservoir and Mohawk
against the Hudson's contamination with polychlorinated biphenyls
and its upriver discharge from industrial operations and wastewater
treatment plants.
The team eventually chose the Hudson because of its ample
capacity for drawing water over the long term. The project
team launched a careful investigation and analysis that incorporated
input from various regulatory agencies, a close understanding
of the interplay with a regional canal system and the need
to convince Halfmoon residents that the Hudson was the best
choice.
The team then helped the town secure more than 15 permits
or approvals from agencies such as the U.S. Environmental
Protection Agency, the Army Corps of Engineers, the U.S. Coast
Guard, the state departments of health and environmental conservation
and even the New York State Thruway Authority. The team navigated
through some approvals by using pre-permit application meetings
and conference calls to build early consensus and identify
relevant issues prior to final design and construction.
With an overall fast-track schedule, the project players-including
six prime contractors and more than 50 minor subcontractors,
suppliers and equipment manufacturers-used a team-oriented
attitude and concentrated communication to ensure success.
At the design and construction phase, the team first had
to acquire two parcels and eight easements for the facility
and infrastructure. Then it had to ensure the river bottom
near the site was deep enough to provide sufficient raw water
intake.
The team scheduled dredging between November and April in
order to avoid interrupting river shipping and boating activities.
That also required a tight review time frame with regulatory
agencies.
Once construction began, the team had to make adjustments
for high water levels in the river during parts of 2002. The
team also met a project goal to quickly complete the exterior
of facility buildings, which enabled the general, plumbing,
HVAC and electrical contractors to work indoors during the
winter.
In the end, the project came in under budget and is supplying
drinking water that meets state Department of Health standards.
"This project looks like it was similar to tuning a watch,"
one jury member said. "The politics and processes were
very challenging."
The facility now operates using an advanced automated SCADA
system, which turns on pumps, opens valves and detects alarm
conditions based on the town's needs. The town also has the
capability to double the plant's capacity in the future.
|