|
Borgata Hotel, Casino & Spa
The building of the Borgata Hotel, Casino & Spa - the
largest construction project undertaken in Atlantic City's
history - required several project teams, which meant that
as the job progressed, communication between the teams was
vital.
"They managed this massive project with separate teams
for each element," a jury member said in describing the
process. "Making sure that each team was talking in the
middle of the night so someone didn't dump dirt where another
crew was supposed to drive piles the next day was a real challenge."
Project officials described the process as a "multi-front
army approach" whereby management teams and workers were
divided into three groups to simultaneously build the low-rise
portion, including the casino, restaurants, retail and parking;
the 43-story guest room tower and infrastructure; and landscaping.
The $1.1 billion, 4.2 million-sq.-ft. resort includes a 43-story
tower on a 30-acre site with 3,100 trees. It features 2,002
guestrooms and suites, 125,000 sq. ft. of gaming space, parking
for 7,100 cars and a 50,000-sq.-ft. European-style spa. It
has 11 retail boutiques, 11 restaurants, a 1,000-seat theater,
a 15,000-sq.-ft. indoor pool/garden complex and 70,000 sq.
ft. of event space.
At the height of construction, nearly 2,200 workers were
on the job.
Despite its massive size - the size of the site is comparable
to 233 football fields - the project was completed on a fast-track
schedule of 33 months.
The Borgata was built on a barrier island over a former landfill,
which necessitated using steel pipe piles. A total of 3,803
piles weighing 225-tons each were driven 60 to 65 ft. into
dense sand for the 17-acre building footprint.
A shallow water table called for extensive dewatering of
the site, construction of a new water treatment unit, retaining
walls and a large volume of imported soil to provide proper
remediation. Four foundation mats totaling 24,600 sq. ft.
required roughly 730 tons of reinforced steel rebar and 8,460
tons of concrete delivered in 150 trucks. If placed end-to-end,
the total length of the mats would be longer than a football
field.
About 35,000 shrubs, 10 acres of wildflowers and seven acres
of sod comprised the landscaping. Among the 3,100 trees planted,
850 were mature Colorado blue spruces. It took 10 months to
locate all of the plant varieties used at the site.
Every plant was imported and situated with the help of 3-D
computer imagery, and workers installed 69 mi. of irrigation
pipes to keep the plants healthy.
"The environmental issues and solutions on this job
were spectacular," remarked a jury member.
The unique shape of the hotel and strong winds off the Atlantic
Ocean meant that the building's structural system had to be
fine-tuned using wind tunnel analysis. A wind tunnel study
was conducted to investigate the structure's response to hurricane-force
winds. Shear walls were strategically located to best resist
the wind loads and concrete as high as 9,000 psi was used
in the walls.
The structural engineers developed a composite structural
steel frame with bolted moment connections and a cellular
deck system for the floors in the Borgata's low-rise component.
Because of the open nature of the interior, transfer trusses
were used to avoid using too many columns.
To construct the high-rise tower, workers used a cast-in-place
post-tensioned concrete flat plate system as a frame. This
system created thinner slabs and greater floor-to-ceiling
heights that resulted in more spacious rooms. Workers poured
approximately 100,000 cu. yds. of concrete for the frame and
used 30,000 tons of steel rebar in only 13 months to reach
the tower's height.
Interior construction began while the exterior was still
unfinished by using temporary "roofs" on the 14th,
24th and 34th floors to prevent water, cold and heat infiltration.
Because of a lack of electrical service, temporary chillers
were brought in to keep the interior cool and humidity free.
|