|
Cross Bronx/Bruckner Interchange
Renovation
Cost: $204 million
Development Team
Owner: New York State Department
of Transportation, Long Island City
Construction Manager: HAKS Engineers,
NYC
General Contractor: DeFoe Corp.,
Mount Vernon, N.Y.
Design Engineer (Interchange):
Hardesty & Hanover Consulting Engineers, NYC
Design Engineer (Roadway): Liro
Kassner Inc., Syosset, N.Y.
Design Engineer (Throgs Neck southbound
over westbound CBE): Infra Tech
Associates, NYC
Design Engineer: (ITS): Parsons
Brinckerhoff Quade & Douglas Inc., NYC
Construction Inspection Consultant:
Edwards & Kelcey Engineering, Inc, Morristown, N.J.
Construction Inspection Consultant:
Haider Engineering, Brooklyn, N.Y.
Concrete Contractor: United
States Rebar Inc., Freeport, N.Y.
Precast Concrete Contractor:
CPI Constructors/Consultants, Bronxville, NYC
Steel Erector: DeFore-Rice JV,
Mount Vernon, N.Y.
Electrical Contractor: Hellman
Electric Corp., Whitestone, N.Y.
Welding Consultant: JB Welding
Inc., Cincinnatus, N.Y.
The Cross Bronx Expressway has been congested ever since
it cut its way across the Bronx in the 1950s.
The connection of the Cross Bronx to the Bruckner Expressway,
which links it to the Whitestone and Throgs Neck bridges into
Queens as well as to the New England Thruway, is one of the
most trafficked interchanges in the region. It carries an
average of 250,000 vehicles everyday.
Given its age and level of usage, it was no surprise that
a decade ago when the New York State Department of Transportation
investigated the condition of the interchange, it found some
serious structural and design problems. They included a severely
deteriorated reinforced concrete deck, fatigue-prone details
and seismic-deficient rocker bearings, insufficient horizontal
and vertical stopping sight distances and insufficient merging
distance for the center lanes between the westbound Cross
Bronx and the southbound Bruckner.
To renovate/redesign/reconstruct the interchange took the
combined efforts of four engineering firms coordinated by
HAKS Engineering, which functioned as construction manger.
Work began in 1999 and was completed in June 2002, a year
ahead of schedule and about $36 million below projected costs.
The project included the reconstruction of 14 ramps and bridge
structures along with portions of the Cross Bronx, Throgs
Neck, Bruckner and Hutchinson River Expressways.
In order to maintain the same volume of traffic during construction,
a temporary elevated structure with an open grid deck was
designed to carry two exit lanes of the westbound Cross Bronx
to the southbound Bruckner. Another portion of the slab was
modified to carry one lane of traffic from the eastbound Cross
Bronx to the Whitestone Bridge. This temporary ramp resulted
in significant traffic flow improvements, so the DOT decided
to keep it as a permanent one.
The interchange's old 7.5-in. deck was replaced by an 8.5-in
deck for 130 spans, a process that involved pouring one million
sq. ft. of concrete. Widening 20 spans of the eastbound Cross
Bronx included expanding the abutments and replacing the existing
two-column concrete piers with three-column piers in several
locations.
The old steel box girder cap beams were demolished in stages
and replaced with reinforced concrete cap beams at three piers.
In order to improve sight distances, the top of the retaining
and abutment walls were modified.
The on-grade work included milling of asphalt pavement; repair
of concrete pavement; modifying drainage structures; construction
of flush shoulders; resurfacing roadways, ramps and shoulders;
and installing new lighting.
Finally, closed-circuit TV cameras were installed to monitor
traffic then inform motorists of traffic conditions via new
electronic message boards.
|