The Reconstruction
of the Times Square Station Complex
Development Team
OWNER: Metropolitan Transportation Authority/New
York City Transit, NYC
ARCHITECT AND PLANNERS: William Nicholas Bodouva
& Associates, NYC
ARCHITECT: Kohn Pedersen Fox Associates, NYC
STRUCTURAL & CIVIL ENGINEER: Vollmer Associates,
NYC
MECHANICAL, ELECTRICAL & PLUMBING ENGINEER: Mariano
D. Molina, PC, NYC
ARTIST DESIGN COLABORATOR: Metropolitan Transportation
Authority Arts for Transit, NYC
GENERAL CONTRACTOR: Slattery Skanska Inc/Gottlieb
Skanska Inc., a joint venture, Whitestone, NY
CONSTRUCTION MANAGER: Bovis Lend Lease LMB Inc/CTE
Engineers, a joint venture, NYC
Speeding on track and into the 21st Century is the Times
Square subway station. Serving as a hub for the New York City
Transit system, this complex needed to be brought up to date
and expanded to meet the needs of a growing traveling public.
Serving as a conductor for this growth was the first phase
of the $83 million Reconstruction of the Times Square Complex.
Included in the project was the expansion of the 41st Street
and Seventh Avenue mezzanine. This part of the project required
demolition and excavation of the subway roof. Workers had
to relocate and temporarily support major utilities below
the roadway and then install a complex decking system to allow
traffic to run smoothly overhead while construction took place
underground.
There was also extensive demolition and the new construction
of stairways, concrete floors, platforms and precast glass
block sidewalk panels. In addition, fare arrays were relocated
and there was a need for extensive electrical, signal and
minor mechanical and plumbing work. Architectural elements
included the installation of metal rails and floor and wall
tile, including several types of ornate mosaics. Another aesthetic
improvement was the construction of an ellipse, a vertical
cut through the center of the Broadway mezzanine to provide
passengers with a view of the interior perimeter.
Construction of the new mezzanine had to take place at a lowered
elevation and in the same location as an existing pedestrian
corridor that was not in service. To do this required a reduction
of 18-in. in the floor beam length over the subway tracks.
A special compact fabricated steel section was also used in
the new framing to accomplish this task.
In addition, the street decking used during construction could
not change the existing street grade by more than six-in.
Due to this constraint. The amount of utilities and the fact
that decking had to be limited to 22-in. thick, 12-in. decking
beams with small spans were required.
A phased schedule was developed so the work could be performed
while the station remained operational. In addition, parts
of platforms and entrances required temporary closure to minimize
disruption to passenger flow and station operations.
The jury said, "the challenges faced by this project
team included performing construction while keeping the station
operational, making what was once two stations into one and
site logistics." They praised the project team for developing
"innovative solutions, including a wider 7th Avenue passageway."
|