UBS Warburg,
Phase IIA: Trading Floor Expansion Project
Development Team
OWNER & DEVELOPER: UBS Warburg, Stamford, Conn.
ARCHITECT: Skidmore, Owings & Merrill, NYC
STRUCTURAL ENGINEER: Thornton-Tomasetti Engineers,
NYC
MECHANICAL, ELECTRICAL & PLUMBING ENGINEER: Cosentini
Associates, NYC
GEOTECHNICAL ENGINEER: Langan Engineering & Environmental
Services, Elmwood Park, NJ
TELECOMMUNICATIONS CONSULTANT: Walsh-Lowe & Associates
Inc., Stamford, Conn.
DRYWALL CONTRACTOR: A&A Drywall & Acoustics
Inc., Milford, Conn.
ELECTRICAL CONTRACTOR: Belway Electrical Contracting,
Elmsford, NY
STRUCTURAL STEEL CONTRACTOR: Cives Steel, Gouverneur,
NY
MECHANICAL CONTRACTOR: Harry Grodsky & Co. Inc.,
Springfield, Mass.
SCAFFOLDING & HOISTING CONTRACTOR: Regional Scaffolding
& Hoisting Co. Inc., Bronx, NY
FOUNDATION & CONCRETE SUPERSTRUCTURE CONTRACTOR:
Tri-Star Building Corp., Pleasantville, NY
CONSTRUCTION MANAGER: Turner Construction Co., NYC
The $100 million UBS Warburg, Phase IIA: Trading Floor Expansion
Project was faced with as many challenges as a corporate takeover.
Project challenges included a 23-month schedule, working in
an occupied facility, seamless tie-in work, water prevention,
matching materials and zero downtime.
To resolve these issues, the project team created the world's
largest trading floor - equal to the size of two football
fields.
The trading floor is the upper level of a 338,000-sq.-ft.
addition to an existing building. At the tie-in location,
there was an operating trading floor, data center, offices
and parking garage. Beam pockets for the steel connections
at each floor and at the roof were cut into the building.
The connecting shift crew proceeded through three months of
nights and weekends with selective structural demolition and
extensive welding to accept the new structural steel. Many
of the connections wee directly over windows where trading
floor desks were located. The building structure required
a total of 54 connections to the existing building plus an
additional 27 connections at the curved roof. Once the connections
to the existing building were in place, the structural steel
erection was quick.
The solution to keeping the trading floor operational - even
when trading desks were literally 3-ft. away from the new
construction, a temporary wall partition was constructed at
each floor.
The interior of the trading floor was completed by fully scaffolding
the trading floor ceiling with a hung platform. The platform
was set in steps from the floor the curve of the ceiling.
The open-ended walls were installed with conventional scaffolding.
This coordinated system allowed the trading floor's double
access floor system to be simultaneously installed with the
ceiling.
In order to mange the project with a 23-month construction
schedule, the project team developed an up front, logic-driven,
critical path schedule to plan and monitor the pre-construction
and construction processes. Maintaining the schedule also
required significant preplanning to ensure that the bank's
daily operations were not interrupted.
One of the most challenging aspects of the project was working
on an occupied facility. From blasting rock to steel erection,
to pouring concrete through furniture installation, great
care was taken to ensure the safety of all UBS employees by
construction a 12-in. thick wall to separate them from the
construction.
To seamlessly tie-in the new building to the existing one,
lasers were used to align walls, floors and ceilings. The
challenge of water prevention was met by taking great care
in installing the waterproofing system.
To match materials with the existing structure, the architect
produced an elaborate submittal process for naturally occurring
materials such as wood and granite. The engineer was required
to insure redundancy to avoid downtime - a mandate for keeping
this type of business operational during construction.
The jury recognized this project's team for meeting the challenge
of keeping the existing trading floor operational during construction
and for performing the required work on a constrained site
next to the existing structure.
|