Winter Garden
Reconstruction
Development Team
OWNER: Brookfield Financial Properties, NYC
DESIGN ARCHITECT: Cesar Pelli & Associates, NYC
PRODUCTION ARCHITECT: Adamson Associates. Ontario
STRUCTURAL ENGINEER: Thornton-Tomasetti Engineers,
NYC
MECHANICAL, ELECTRICAL & PLUMBING ENGINEER: Flack+Kurtz
Inc.
SCAFFOLDING & SHORING CONTRACTOR: Atlantic-Heydt
Corp., Maspeth, NY
CONSTRUCTION MANAGER: Turner Construction Co., NYC
Amidst the dust and debris at Ground Zero, another project
team feverishly worked to restore a well-known structure damaged
by falling debris from the North Tower of the World Trade
Center. With a 12-month schedule, a difficult work environment
and a desire to succeed, the project team for the reconstruction
of the Winter Garden at the World Financial Center set out
to accomplish a daunting task.
When the debris from the North Tower fell, it destroyed a
bridge connecting the Winter Garden to the North Tower. When
the bridge collapsed, it pulled on the eastern end of the
Winter Garden, bending the semi-circular ring girder at the
front of the building.
Since this was a primary support for the structure, the ring
girder had to be "straightened." To do this, bent
portions of the semi-circular girder were cut out and replaced
in pieces.
Simultaneously, the New York City Department of Design &
Construction postponed debris removal until the structure
could be shored and braced to ensure the overall safety of
the building and the surrounding area.
Immediate efforts were made by the project team to install
shoring towers. This presented great difficulties because
the weight of the structure had to be transferred, increasing
the chances for even more damage or possibly structural collapse.
Repair and reconstruction was required to broken roof arches,
floor framing, the lateral support system and the exterior.
This daunting task was complicated by a tight schedule that
mandated completion by September 11, 2002.
To preserve as much of the existing structure as possible,
sophisticated analyses were performed which resulted in the
development to repair the damaged but restorable elements
of the structure and to distribute the jacking stresses to
the undamaged portion of the structure.
This included construction of a trolley car system to replace
the glass. This system consisted of a four-scaffold system
over the roof arches. The trolley could move side to side
and up and down along the exterior of the Winter Garden. This
helped to expedite glass roof panel erection and used the
roof shoring towers as support for a temporary, intermediate
protective platform located between the main floor and the
roof. This allowed for the simultaneous replacement of the
skylight, the overhead glazing in the atrium and the stone
work below. This system allowed the skylight to be installed
in 18 weeks compared with 30 months it took to install it
when the building was first constructed.
The rebuilding of the east facade used the contemporary Pilkington
Curtain Wall Glass system rather than the original stone facade
to facilitate the project.
To ensure that the project schedule would be met, the project
team worked around the clock. In one instance, they went straight
from design drawings to construction documents and in other
instances they expedited material shipments, including the
60,000-sq.-ft. of Italian stone for the floor and walls.
A team approach was evident throughout the project. An emotional
investment was made by hundreds of people who wanted the Winter
Garden restored on time and better than it had been.
"The project team," the jury said, "took the
Winter Garden from a structural nightmare to a complete project
in a very short period of time. It is a good engineering project.
Its completion gave a lift to the city and the design improved
on the visibility from West Street."
|