Exterior Restoration
of the MetLife Tower
Development Team
OWNER: Metropolitan Life Insurance Co., NYC
ARCHITECT & STRUCTURAL ENGINEER: Robert Silman
Associates, NYC
HISTORIC PRESERVATION CONSULTANT: Building Conservation
Associates Inc., NYC
SCAFFOLDING CONTRACTOR: Regional Scaffolding &
Hoisting Co., Bronx, N.Y.
MASONRY CONTRACTOR: Graciano Corp., Pittsburgh, Pa.
WINDOW SUBCONTRACTOR: Airmaster Window Systems Inc.,
Larchmont, N.Y.
WINDOW CONSULTANT: Gordon H. Smith Inc., NYC
LIGHTING CONSULTANT: Horton Lees Brogden Lighting
Design Inc., NYC
CONSTRUCTION MANAGER & GENERAL CONTRACTOR: Structure
Tone Inc., NYC
It is a landmark among the office towers on Madison Avenue
and one of the more recognizable structures in the city's
skyline. As such, the restoration of its exterior - a painstaking
and time-consuming task - took many years.
To implement the $35 million restoration of the exterior of
this beautiful structure at 1 Madison Avenue first required
erection of a 55-story scaffold to access the facade in order
to do the necessary repair work.
Initially, 4,000 facade deficiencies were earmarked for repair
and restoration, but it was soon discovered that 10,000 deficiencies
need to be addressed, including rigging 2,000-lb. pieces of
stone out of the building and replacing them.
The heart of the project consisted of three different combinations
of scaffolding and hoists to facilitate the work. One was
an exterior hoist that allowed access to the fixed scaffold
on the building, but due to weight constraints, the scaffold
was planked every second floor. In addition, the scaffold
was kept 3 ft. away from the building at all times. Inside
each 3-ft. cavity were 16 electric hanging rigs to allow movement
up and down along the facade and to feed personnel and materials
off the scaffold.
Work also include repointing the entire limestone and Tuckahoe
marble structure, replacing 1,100 historic windows, re-gilding
the building's gold dome and installing a new computer-controlled
lighting system to be installed on the entire building.
The restoration also included all four clocks on the building,
replication of glass tiles that needed replacement, and removal
of all of the bronze frames that served as the hour and minute
marks on the clock so that they could be refurbished, reinstalled,
recaulked and reglazed.
Because the building is a landmark, a solution needed to be
devised to allow it to remain visible while work was performed
on a building that had to remain operational. To achieve this,
netting was installed around the scaffold that allowed the
tower to still be visible.
To deal more safely with the stone on the building, which
presented unique anchorage conditions, a combination of different
anchorages were used.
Locating Tuckahoe marble to replace the damaged Tuckahoe marble
was also difficult. Since Tuckahoe marble quarries had been
closed for decades, it became a quest to locate the required
material. The search for the material led to the discovery
of a "sedan-sized" boulder of the marble in a service
station. After the owner purchased it, it was sliced into
3-in. slabs, trucked to the site and then carved into "Dutchman"
repair pieces. The carving took place in a makeshift stone
yard on the building's roof. A drove was used on the new slabs
so they could match the original slabs while others were sandblasted
to match older stone. The marble was supplemented with white,
gray and buff cast stone and with salvaged marble from the
new Columbia University boathouse in Inwood Hill Park and
from the MetLife tower itself.
The jury said this project was "inherently complicated
by its size and therefore required great attention to detail
while re-establishing the lost art of tile setting."
|