Marriott Conference
Hotel at Lafayette Yard
Development Team
OWNER & DEVELOPER: Acquest - New Jersey LLC,
Bloomfield Hills, MI
ARCHITECT: JVA (Ford Farewell Mills & Gatsch
Architects, Princeton), NJ
DESIGN ARCHITECT: JVA (Johnson Jones), Princeton,
NJ
INTERIOR DESIGNER: CUH2A Inc., Princeton, NJ
STRUCTURAL ENGINEER (HOTEL & CONFERENCE CENTER):
Harman, Cagley & Associates Inc. of King of Prussia,
Pa.
STRUCTURAL ENGINEER (PARKING STRUCTURE): Carl Walker
Inc., Haddon Heights, NJ
MECHANICAL, ELECTRICAL & PLUMBING ENGINEER: Giovanetti
Shulman Associates, Drexel Hill, Pa.
ELECTRICAL CONTRACTOR: Kleinknecht Electric Co.,
Fairfield, NJ
PLUMBING CONTRACTOR: B. Trematore Plumbing &
Heating, Fairfield, NJ
EARTHWORK CONTACTOR: Interstate Industrial Corp.,
Clifton, NJ
AUGER CAST PILE CONTRACTOR: Berkel & Co. Contractors
Inc., Pasadena, Md.
MASONRY CONTRACTOR: Davis Giovinazzo Construction
Co., Spring House, Pa.
DRYWALL, CEILING AND CARPENTRY CONTRACTOR: Interstate
Drywall Corp., Clifton, NJ.
CONSULTANT: Zeiger Enterprises, Trenton, NJ
HOTEL OPERATOR: Marriott Corp., Washington, DC
CONSTRUCTION MANAGER: Turner Construction Co. of
Somerset, NJ
"Location, Location, Location" is a well-known
credo in real estate. The location of a project, however,
can present high hurdles for the construction team before
a project is ever completed.
The development team for the $38.5 million Marriott Conference
Hotel at Lafayette Yard in Trenton, N.J., was presented with
such challenges - challenges that included being next to a
war memorial, an historic district and a creek. And the design
also had to go through a landmark approval process.
Outreach also became an important part of this project because
the project was the creation of a public-private not-for-profit
organization, Lafayette Yard. As a result, the community was
involved in the utilization of manpower, vendors and subcontractors.
In addition, the site turned out to be a brownfield as well
as an archeologically rich historic property with important
18th Century and 19th Century mills on it. In one case, the
18th Century mill could not be disturbed, while foundations
from a number of 19th Century mills forced the construction
team to do "workarounds." In other cases, soil had
to be removed and recompacted so piles could be driven because
the land is a flood plane. As a result, a decision was made
to use slab on grade foundations. It also resulted in the
state setting a higher standard for the flood plane - 500
years instead of 100 years - because of its size.
The solution to the flood plane was a two-part foundation.
One part includes a liner installed on grade, while the second
part, the foundation for the garage, serves as a cap, protecting
an area considered part of the brownfield. The cap also prevents
groundwater from leaching and getting into the groundwater
system.
In addition, the Assunpink Creek is located on the south side
of the site, adjacent to it. The challenge was to address
the nonurban side of the site. The solution was to create
a courtyard where the hotel lobby could spill out on to it
and the restaurant from the conference center.
The facility was designed to be very urban on Lafayette Street,
but the south side of the site is contiguous to the creek
and the river and as a result, there is a more picturesque
landscape. Thus, there are two environments in the same building,
respecting both sides of the site.
The project features two framing systems. The hotel features
prestressed, precast, hollow-core concrete plank, which is
supported on reinforced masonry load bearing walls. The load-bearing
walls go down to a foundation system of pile caps and grade
beams on auger cast piles. To provide for atrium space at
the ground floor, structural transfer beams had to be introduced
to provide clear spans. This system features unusually high
75-ft. masonry walls.
The conference center has a separate framing system made of
structural steel with composite beams and slab on metal deck.
The foundations for the conference center are also auger cast
piles with grade beams. The reason for this type of foundation
system was the result of poor soil conditions in some areas
of the site.
Perhaps the project team's most difficult task was how to
ensure the design and construction of the project without
exhausting the owner's financial resources given the fact
that the property was contaminated. The subsurface conditions
required extensive analysis for the foundation systems used
because of unsuitable soil conditions for bearing capacity.
The solution was to use a combination of caissons and piles
for a cost-effective foundation.
The jury called this a difficult project whose team embraced
the community, its vendors, small business enterprise, women
business enterprise and minority business enterprise contractors
and the concept of adaptive reuse of a brownfield site in
the heart of a major metropolitan municipality.
|