Robert Angelillo is an attorney with
Meyer, Suozzi, English & Klein PC, in Garden City,
N.Y., practicing construction law and litigation.
|
N.Y. Renders Final Word on "Pay-if-Paid" Contracts
The state's high court finally
chooses sides in a judicial debate over whether certain
subcontractors can be governed by another state's law.
by Robert C. Angelillo
In 2005, two state appellate courts, one in Manhattan and
one in Brooklyn, issued conflicting decisions about the enforceability
of certain "pay-if-paid" subcontracts.
Although the construction industry thought it had seen the
last of these subcontracts in 1995, when New York's highest
court found them to be unenforceable in West-Fair Electric
Contractors v. Aetna Casualty & Surety Company, the 2005
decisions addressed a loophole that brought the issue back
to the fore.
In the original West-Fair decision, the Court of Appeals
barred the use of pay-if-paid subcontracts, which permit a
contractor to withhold payment from a subcontractor until
the contractor itself receives payment from the owner. It
held that these contracts were against New York's public policy
because they could prevent subcontractors from enforcing properly
filed mechanics' liens.
However, in 2005, the appellate court in Manhattan found
that West-Fair did not dispose of all pay-if-paid subcontracts.
In the case, Hugh O'Kane Electric Company, LLC v. MasTec
North America, Inc., the Manhattan court found that if a contractor
and subcontractor agreed to use another state's law to control
their subcontract, and that state allows pay-if-paid contracts,
then such a subcontract would be enforceable, regardless of
West-Fair's public policy considerations. While this decision
only directly affected courts in Manhattan and the Bronx,
it was an eye-opening decision for all courts in the state
because it seemed to conflict with the principles of West-Fair.
Several months after the Hugh O'Kane decision, Brooklyn's
appellate court issued a decision in another case, Welsbach
Electric Corp. v. MasTec North America, Inc., that came to
the exact opposite conclusion as the Manhattan court. The
Brooklyn court found that even if another state's law controlled
the contract, and that state permitted pay-if-paid contracts,
a New York court should not enforce the pay-if-paid provision
because New York's public policy discussed in West-Fair was
too important.
Because of these conflicting decisions, contractors who used
courts in Manhattan and the Bronx could enforce their pay-if-paid
subcontracts if another state's law controlling their contracts
permitted them, while contractors using Brooklyn courts -
as well as courts in Long Island, Westchester, and others
in the state - could not.
This set the stage for the state's highest court, the Court
of Appeals, to step in and render a statewide decision on
the issue. It did just that in November after the contractor
in the Welsbach case, MasTec, appealed the Brooklyn appellate
court's ruling. The result: the contractor in both cases,
MasTec, won.
In the Welsbach appeal, the Court of Appeals focused on the
right of contracting parties to choose the state law that
they wanted to apply to their subcontract. The high court
agreed with the appellate court in Hugh O'Kane and found that
the public policy discussed in West-Fair was simply not important
enough to overcome this right.
Therefore, the Court of Appeals found that, when the contracting
parties agreed that another state's law applied to their subcontract,
and that state permitted pay-if-paid contracts, those subcontracts
could be enforced in any court in New York.
So, what is the overall effect of the Court of Appeals decision?
On a practical level, it means that a contractor who has pay-if-paid
provisions in a subcontract controlled - and permitted - by
another state's law can refuse to pay a subcontractor until
the contractor itself receives payment from the owner.
However, the broader impact of the decision is limited due
to another factor. A law passed by the New York Legislature
and signed by Gov. George Pataki in 2003 forbids contractors
and subcontractors from choosing another state's law in all
construction contracts entered into after Jan. 14, 2003. By
requiring use of New York law, the parties must adhere to
West-Fair, which bars pay-if-paid contracts.
While this law applies to most contracts entered into after
Jan. 14, 2003, it does not apply to subcontracts entered into
before that date, or for subcontracts entered into after that
date on projects that had already been in existence. Therefore,
the new court decision only directly affects subcontracts
older than January 2003 and recently entered subcontracts
on long-existing projects.
However, perhaps more importantly, the Court of Appeals decision
in the Welsbach appeal seems to diminish the key point of
the West-Fair decision - that protecting subcontractor rights
under the New York lien law is a fundamental public policy
of this state.
If the right to choose another state's law is more important
than the right to enforce a mechanics' lien, what, if any,
other considerations will also triumph over the lien law in
the future? Only time, and future court cases, will tell.
|