Lori
Samet Schwarz is a principal at Zetlin & De Chiara, a
law firm in New York that serves the design, construction,
and real estate industries. |
Liquidating Agreements Can Streamline Litigation
Even when parties on a project
do not have a contractual relationship, liquidating agreements
may still allow recovery for damages.
by Lori Samet Schwarz
As construction projects become ever more complex, they amass
a growing number of subcontractors and subconsultants. When
there are significant changes to the scope of work or delays
on a project, it is no longer just the owner and prime contractor
who play the "blame game" - subcontractors today
often contend that they have incurred damages as a direct
result of an owner's conduct.
However, because a subcontractor is not in direct privity
with the owner - meaning that the two entities do not have
a contractual relationship - the subcontractor is limited
to asserting its claims against the prime contractor that
hired it. The prime, in turn, is left to try and recover those
damages from the owner. Similarly, an owner can be damaged
or delayed by a subcontractor's inadequate performance, yet
the owner cannot assert its claims directly against that firm.
What results is often lengthy and costly litigation, particularly
when the general contractor's prime contract does not impose
the same liabilities as its subcontracts with subcontractors.
As a result, liquidating agreements have become a useful tool
to "bridge the privity gap between owners and subcontractors
who sustain damages as a result of the others' actions,"
as stated in North Moore Street Developers v. Meltzer/Mandl
Architects, a recent court decision in New York's Appellate
Division, First Department.
The court faced an unusual spin on the topic, because the
owner-developer of the project, North Moore Street Developers,
had entered into a liquidating agreement with R.C. Dolner,
the general contractor. In the agreement, the owner acknowledged
and admitted liability for certain damages arising out of
its own architect's errors, omissions, or design defects.
The owner also agreed to liquidate that liability in the amount
recovered from the architect and further agreed to pass through
to Dolner the amount recovered from the architect on its behalf.
The agreement essentially allowed the owner to assert professional
malpractice claims Dolner had made directly against the project
architect, Meltzer/Mandl - even though there was no privity
between the contractor and architect.
However, Meltzer/Mandl filed its own causes of action against
various project parties. When third-party subcontractor defendants
moved to dismiss the architect's causes of action, Meltzer/Mandl
cross-moved to dismiss the owner's causes of action for damages
claimed on behalf of Dolner. While a trial court had decided
in favor of Meltzer/Mandl, the appellate court reversed that
ruling and went to great lengths to instruct the trial court
judge in how to properly apply the law.
Specifically, the appellate court raised two issues: (1)
whether an owner can assert its independent claims against
an architect in addition to those of the general contractor,
and (2) whether an owner can enter into a liquidating agreement
and admit liability to its general contractor even where it
does not have any contractual liability. On both questions,
the court answered yes.
The court cited another New York appellate court decision
from 2001 in Bovis Lend Lease LMB v. GCT Venture, which states
that to be enforceable "[l]iquidating agreements [must]
have three basic elements: (1) the imposition of liability
upon a party for a third party's increased costs, thereby
providing the first party with a basis for legal action against
the party at fault, (2) a liquidation of liability in the
amount of the first party's recovery against the party at
fault, and (3) a provision for the pass-through of that recovery
to the third party."
In North Moore, the owner pointed to its contractual liability
under the agreement with Dolner for delays caused by the owner
itself and by those under its agency and control, such as
the architect. The owner's complaint alleged that the architect's
professional malpractice caused delays in excess of the 70
days provided in Dolner's contract, forming the basis for
the owner's liability to Dolner.
While North Moore Street involves an unusual set of facts
because the owner joined forces with the contractor against
its own architect, it demonstrates the potential to streamline
litigation by allowing for the creation of alliances that
best suit the needs of the parties in the project. By picking
the right relationships, litigants can focus on the primarily
culpable party and circumvent the need for contractual privity
in order for project grievances to be made whole.
|