|
Better Protection for Contractors on Hybrid
Projects
Recent changes to New York State's
lien law has given contractors a better chance to recover
payments on public-private hybrid projects that had long presented
a risky business proposition.
By Henry Goldberg
One of the frustrating loopholes in the lien law in New York
had historically been the inability of claimants to file liens
against privately funded projects on public land. A recent
amendment to the state's law appears to offer some relief
to this longstanding problem.
The lien law generally provides contractors, subcontractors,
and certain other project participants with a chance to recover
unpaid sums beyond the typical breach of contract claim. Generally,
the law allows the lien on a private project to go against
the owner's interest in the land itself, while on a public
project it would go against the public funds dedicated to
the job. In either case, a properly filed lien protects the
lienor in the event that a contractor goes out of business
or a project dies.
However, these so-called hybrid projects involving private
development on public land defied the process. With the land
in public hands, the lienor could not file a claim against
the property, and with investment from private sources, it
also could not attach to public funds.
These projects are not uncommon. Many state universities,
for instance, develop projects on public land using funds
from affiliated but privately operated foundations.
While most hybrid efforts eventually found project teams,
some contractors had been reluctant to bid on them because
of the inability to file liens. Without liens, subcontractors
had no remedy on a hybrid project if the general contractor
were to go out of business.
An amendment to the law in 1992 diminished the loophole in
that it allowed contractors and suppliers to file a private
improvement mechanic's lien against the real property owned
by an Industrial Development Agency. The change was meant
largely to recognize that while the IDA may be the owner of
the property, the "beneficial owner" is a private
entity, and as such, the project constitutes a private and
not a public improvement.
Last November, another amendment to the lien law took effect
that may greatly expand the protection available to contractors,
subcontractors, and suppliers. The recent change requires
all private owners to post a surety bond or "other form"
of security that can guarantee payment for privately funded
projects located on publicly owned land. The change applies
to instances where estimated construction costs exceed $250,000.
While the amendment does not technically allow the filing
of a mechanic's lien, it is a significant step toward closing
the loophole. It may well give contractors, subcontractors,
and suppliers the cover they need to bid on a project, because
suing on a payment bond is ordinarily an easier remedy than
having to go through the formalities of foreclosing on a mechanic's
lien.
The amendment is not foolproof. For instance, it sets no
minimum or mandatory terms for the bond, meaning that it behooves
the project participant to find out the exact terms of the
bond prior to executing a contract. Those terms could include
restrictive notice provisions or short filing periods that
a party would have to meet in order to preserve a claim against
the bond.
Likewise, the amendment leaves the status of projects with
construction budgets under $250,000 without the bond payment
protection. As of the writing of this article, there are no
further amendments on the table.
It will take time to see how the amendment works and whether
further legislative action is necessary. But the recent changes
at least give building industry participants a few extra tools
to work with as they pursue new projects.
Henry Goldberg is managing partner of
Goldberg & Connolly, a construction and government contracting
law firm based in Rockville Centre, N.Y.
|