|
When a Deal is Not a Deal
A case pending in federal court
in Manhattan explores whether a contractor can recoup a change
order that it paid "under duress."
By Robert C. Angelillo
The successful replacement earlier this year of New York's
Third Avenue Bridge between the Bronx and Manhattan appeared
to be a model of construction professionals working together
to complete a difficult job.
Nevertheless, it seems that there were troubled waters flowing
under the bridge that have now pitted the general contractor,
KiSKA of New York, and its primary subcontractor, G&G
Steel of Russellville, Ala., against each other in federal
court in Manhattan.
The case hangs on an agreement that settled a large set of
change orders during the project. Though the two sides appeared
to have made a deal, an early ruling from the court said,
effectively, "maybe not."
As construction of the swing-span bridge over the Harlem
River approached a crucial stage, G&G submitted three
change order proposals to KiSKA for work that the steel contractor
deemed to be extra. Although KiSKA agreed that some of the
work was extra, its project leaders contended that most of
the items constituted contract work. Therefore, it initially
refused to pay G&G the requested amount, $1,757,285.
A short time later, the two companies entered into a written
settlement agreement tilted toward the subcontractor's terms,
and KiSKA paid G&G $1.5 million. The $123 million job
for the New York City Department of Transportation proceeded
to completion.
However, afterwards, KiSKA sued G&G for $1,134,722, the
difference of the amount it had paid G&G under the settlement
agreement minus the amount of the one change order that the
two sides had agreed was extra work.
In its response to the lawsuit, G&G argued that it had
a written and signed settlement agreement, and that KiSKA
had entered into the agreement on the advice of its attorney,
a seasoned construction lawyer. In other words, they had a
deal.
The court's decision to let the case proceed, however, means
a deal might not be a deal.
In the lawsuit, KiSKA admits that it signed the settlement
agreement with G&G. However, KiSKA claims that after it
initially denied the change orders, G&G threatened to
stop work if it was not paid for its claimed extras. The plaintiff
claims that had work stopped, it would have subjected KiSKA
to a host of liquidated and other monetary damages, damaged
the company's reputation, and effectively removed it from
consideration for further public work in New York City. It
also asserted that a work stoppage would cause danger and
inconvenience to the public.
KiSKA's lawsuit also claims that the company could not have
obtained a replacement subcontractor to complete G&G's
work in a cost-effective manner that would have avoided these
consequences.
Therefore, despite KiSKA's insistence that there was no legal
basis for G&G's threat to stop work, and even though it
insists it did not owe G&G the full $1.5 million it paid,
the potentially damaging factors listed in the lawsuit gave
the general contractor no alternative but to enter into the
agreement and pay the sum. It claims that it only entered
into the deal under "economic duress," and therefore
asked the court to invalidate it.
And surprisingly, the court agreed with KiSKA inasmuch as
it has let the case proceed.
Generally speaking, under New York law, success on an economic
duress claim is difficult to achieve. It requires proof that
a party made an unlawful threat and that the threat caused
another party to involuntarily accept contract terms because
it had no choice under the circumstances.
However, as noted by G&G in its defense, financial pressure
and a strong bargaining position generally do not constitute
duress. In agreeing to let the case proceed, the court essentially
found that KiSKA's allegations, if proven, could amount to
more than mere financial pressure, and could be considered
economic duress sufficient to undo a signed, written settlement
agreement.
This decision comes at a preliminary stage in the case and
merely allows the claim to be made at a trial, if that occurs.
It does not mean KiSKA has won. As noted by the court, if
G&G proves it was entitled to the amount demanded before
continuing work, it would defeat KiSKA's claim.
Still, it is an important decision with regard to the strategy
employed in negotiating and settling change orders. It certainly
appears to have broadened a traditionally narrow scope of
what constitutes "duress." It also may inspire contractors
to believe that they have a "second bite at the apple"
and a new-found ability to contest disputed change orders
after they have been "settled."
Only time will tell if the court dockets will begin to swell
with economic duress claims. But it is clear that subcontractors
should think long and hard before threatening to hold up a
job over disputed change orders. After the KiSKA decision,
subcontractors may find that they can win the battle and get
paid for change orders during construction, but lose the war
if they have to give money back because a court finds that
the payment constituted unlawful duress.
Robert Angelillo is an attorney practicing
construction law and litigation at Meyer, Suozzi, English
& Klein, a law firm based in Mineola, N.Y.
|