|
Beware the Temptation to Offer Extra Services
Although most professionals aim
to offer their best possible effort to clients, performing
out-of-scope or post-completion services on construction projects
opens the door to greater liability.
By Matthew S. Quinn
Most professionals feel driven to do the best job possible
for clients and do not rest until the client is satisfied.
This common character trait, shared by many in the construction
industry, often manifests itself in the performance of services
beyond the scope for which the professional is retained or
the continuation of services after contract completion.
Construction industry professionals are often more concerned
with the proper and timely completion of a project than with
possible exposure to liability. But this strong work ethic
may present unforeseen risks.
First, a professional who performs services beyond the scope
for which he or she is retained invites exposure to liability
for any negligence on such work. In other words, by agreeing
or deciding on their own to offer services that are not within
the contract's scope, professionals are assuming a duty to
perform within the applicable standard of care. They may be
held liable for negligent performance in the same manner as
if the extra work had been in the contract - even when there
is no additional payment.
A typical case on construction projects occurs when a general
or trade contractor is having difficulty performing its work
and a design professional steps in to assist. An inexperienced
contractor may have trouble coordinating its forces. In order
to keep the project on track, the architect opts to attend
and even lead contractor coordination meetings.
But if the project still faces delays despite the added effort,
the owner and even the contractor may point the finger at
the architect. Though owner-consultant contracts generally
provide that an architect is not responsible for a contractor's
deficient work or its failure to abide by project schedules,
the voluntary assumption of services beyond the contractual
obligations may be enough for a court to impose liability
on an architect.
A second area where good intentions may get industry professionals
into trouble is in the performance of services on projects
even after substantial or final completion of construction.
Again, motivated by a desire to satisfy the client, construction
professionals may undertake services that they are not contractually
obligated to provide - usually for no extra pay.
An example might be where an electrical engineer that has
completed its tasks on a project decides to assist in resolving
an electrical problem that occurs after the owner takes possession
of the building.
Again, professionals performing such out-of-contract post-completion
services are taking on extra liability. But the professionals
may also be stretching the applicable statute of limitations.
In the case of the electrical work, the engineer's voluntary
"remedial" efforts could push out the starting point
of the statute of limitations for future claims until after
those tasks are completed.
In New York, a typical action to recover damages for malpractice
on construction projects must start within three years, regardless
of whether the underlying claim is for breach of contract
or negligence. Unless a contractual provision defines the
time that a statute of limitations begins, the clock generally
starts upon substantial completion of construction.
New York and other states, however, have an exception to
that "substantial completion" standard - the so-called
"continuous treatment doctrine." The doctrine suspends
the accrual of a malpractice cause of action until "treatment"
ends - when the professional relationship finishes. New York
courts have applied it to claims against design professionals.
The doctrine's aim is to encourage an owner to refrain from
filing a claim until the professional has had an opportunity
to remediate any deficient services, in hopes of reducing
the pressure to file a lawsuit within a statute of limitations.
But the effect delays the start of the statute of limitations
term until after the professional's continuous services -
within and beyond the contract scope - have ended.
To borrow from an old phrase, the road to the courthouse
is often paved with good intentions. There are, however, means
to reduce added liability for extra efforts. Construction
industry professionals can negotiate and execute a separate
contract for out-of-scope services that sets caps on liability
or shortens the statute of limitations. At the very least,
the professional should weigh the advantages of providing
such extra services against the possible additional risks.
Matthew Quinn is a partner at Zetlin
& De Chiara, a New York-based law firm that specializes
in construction law.
|