|
It's Smart to Plan Ahead for Change Orders
Project teams can ensure much smoother
paths if they address change orders with explicit contractual
terms, even when plans and specs appear to cover all the bases.
Putting in such extra effort pays off in fewer delays and
fewer unresolved disputes that can add litigation costs down
the road.
By Joseph R. Harbeson
Change orders aren't afterthoughts - they are direct factors
in a project's bottom line. How changes are managed can determine
project profitability, whether work is completed on time,
whether liens are filed and must be dealt with, whether subcontractors
delay the project or walk off the job, and, of course, whether
litigation ensues.
Change orders are important factors even when plans and
specs appear to cover all the bases. Site conditions, changes
in the owner's project needs, changes in sequencing, or other
unexpected events inexorably lead to extra work and payment
claims.
Such issues - and the management and legal costs that can
follow - increase exponentially on large projects, especially
when multiple parties may have a role in approving changes
and processing payments. Keeping control of the change order
process can thus be critical for bringing projects in on time
and at an acceptable budget.
Even routine payment and processing issues can be critical.
When a complex project has numerous interested parties beyond
the owner and GC or CM - such as joint venture partners, lenders,
and consultants - processing significant changes can pose
a danger to project health. Problems with addressing, approving,
and paying for change orders can lead to project delays and
delayed claims, even in the face of contractual "no damages
for delay" clauses. Even when contract provisions disallow
delay claims, New York courts sometimes allow such claims
to move forward in cases where the delays resulted from willful
or grossly negligent conduct, from "uncontemplated delays,"
or from conduct viewed as a "fundamental breach"
of contractual obligations.
Avoiding such problems requires focus and planning from
the outset of a project, and it starts with contract drafting.
Project documents have to be carefully drafted to delineate
the obligations of all parties, each of whom should think
through procedures for the review, approval, and payment for
change orders. If the project lender or a venture partner
has a role in approval of additional costs, or if other parties
must approve change orders, the contract should realistically
assess the time that review will take and build it into the
project agreements, so that the GC and subcontractors know
these parameters from the outset. A subcontractor already
incurring the costs of performing change order work won't
find it satisfactory to hear that previously set approval
and payment time frames cannot be met because the paperwork
required more review.
The AIA A-201 General Conditions, used on many projects
at least as a starting point, provide very little - and frankly,
inadequate - guidance for change order review. Neither Article
7 covering changes in the work, nor Article 4.2, setting out
the architect's duties, impose schedules for change order
approval. While this may suit many owners just fine, it can
be dangerous. To avoid later disputes, having basic guidelines
would be prudent. Another key step is to inform contractors
about all parties who must approve changes, so that even in
the absence of specific contractual deadlines, these project
participants have a realistic idea of how long the approval
process will take.
The contracts and general conditions should also provide
for expedited meetings of all interested parties to be called
on short notice to resolve disputes. These meetings should
not be tacked on to regular job meetings, but focus on extra
work disputes before they affect the project. Expedited mediation
is another possible approach.
Once a project team establishes such procedures, however,
they must use them. That means having sufficient project management
and estimating staff to properly and promptly assess changes.
Having inadequate personnel can lead to cut corners and disputes
that threaten the project. Attorneys involved in change order
disputes too often see that an owner or GC, by trying to save
a little in administration, spends a lot later in litigation.
Hold regular meetings to work out changes, whether or not
the contract requires them. Do not let disputes fester. Finally,
pay for the approved changes promptly, in accordance with
the contract payment provisions.
Joseph Harbeson is a partner at Ruskin
Moscou Faltischek, based in Uniondale, N.Y., where he works
in the litigation department and employment law group and
chairs the construction practice group.
|