|
Making Sure Your Claim is Ripe
It is imperative that before a
contractor begins the dispute resolution process, it needs
to obtain a final determination by the engineer which it can
properly dispute.
By Henry L. Goldberg, Esq
It is axiomatic that obtaining a final determination by the
authorized agency representative, normally the engineer, is
a basic precedent to a dispute arising with a New York City
agency. However, this is often easier said than done. Many
resident engineers simply do not deal with the problem in
a timely fashion. No decision on a thorny construction issue
is often the norm. What is a contractor to do? Many, in frustration,
have attempted to invoke the New York City dispute resolution
process without first obtaining a final decision from the
engineer of the agency with whom they are contracting.
In dealing with NYC agencies, Article 27 of the Standard
Construction Contract defines the process. Article 27, which
is basically identical to Section 4-09 of the Procurement
Policy Board Rules, mandates that before a contractor can
file a notice of dispute with a commissioner, it must first
receive written notice of the engineer's determination or
action which is the subject of the dispute. If the contractor
fails to receive a determination by the engineer, any claim
that is subsequently brought by the contractor will be rejected
as premature. There is no dispute yet to be resolved. This
can be extremely difficult for a construction company that
has poured its resources into a disputed issue and has waited
months, or even years, for a determination from the engineer.
This concept of 'ripeness' was recently considered by NYC's
Contract Dispute Resolution Board. In that case, the contractor
filed a notice of dispute with the NYC-DDC. However, the agency
advised the contractor that the subject matter of the dispute
was under review. Not wanting to be put off any longer, the
contractor submitted the dispute to the NYC Comptroller's
Office. The comptroller did not render a determination. The
contractor then filed its application with the CDRB. The CDRB
ruled that the petitioner's claim for resolution of its dispute
was not properly before the board. The DDC's alleged failure
to respond to the contractor's submission was not the type
of dispute contemplated by the dispute resolution procedure.
The DDC had not as yet denied any of the contractor's claim.
A dispute only arises when the commissioner's representative
makes a final determination with which a contractor disagrees.
The CDRB held that because the engineer had not rendered a
decision, there was no ìjusticiable disputeî
and nothing for the CDRB to decide.
A related problem is that many contractors do not confirm
who is the "Article31" engineer designated
by the particular agency for a particular project. Often a
letter to the commissioner seeking confirmation of the identity
of the engineer is the best way to protect your interests.
On major projects there are simply too many agency representatives
with apparent authority to take a chance in this regard. There
can only be one resident engineer on the project with the
required authority to make a final determination.
An unfavorable determination by the engineer creates the
dispute between the agency and the contractor. Within 30 days
of receiving notice of the determination, the contractor must
file a notice of dispute with the agency's commissioner. It
is interesting to note that a commissioner (unlike his subordinate,
the engineer) is limited to 30 days after he has received
all materials and information from both the contractor and
engineer of the agency to make his determination. Article
27 of the Standard New York City Construction Contract states
that, the "[f]ailure to make such determination within
the time required by this article shall be deemed a non-determination
without prejudice that will allow application to the next
level." In other words, if the commissioner or comptroller
fails to render a decision within prescribed period of time,
the claim may be deemed denied, which allows the contractor
to appeal its claim to the next level, i.e., the comptroller
or CDRB.
Within 30 days of the contractor receiving a determination
by the commissioner, it must file a notice of claim with the
comptroller. The comptroller shall have 45 days from receipt
of all materials and information from the parties to investigate
the claim. This time period can only be extended for an additional
45 days if agreed to by both the contractor and comptroller.
If the claim has not been settled or adjusted by the comptroller
within the time period provided in Article 27, the contractor
may then petition the CDRB to review the commissioner's determination.
In sum, it is imperative that before a contractor begins
the dispute resolution process, it needs to obtain a final
determination by the engineer which it can properly dispute.
Otherwise, in the eyes of the Comptroller's Office or the
CDRB, there is simply no dispute to be decided. If your company
has been hemorrhaging significant sums for months while one
of these disputes is "under consideration," this
can be extremely vexing. Since there is no provision for "deeming"
a resident engineer's inaction a denial, every effort should
be made in the name of fairness to elicit a determination.
Certainly, pushing for a final decision from a resident engineer
may raise concerns about receiving a timely, but adverse,
decision. But not to do so dooms the efforts of any contractor
to timely employ the available NYC dispute resolution procedures.
(Joseph J Sisca III, Esq., an associate
with Goldberg & Connolly assisted with preparation of
the article.)
|