|
A Legal Perspective on the Use and Abuse
of Schedules
The direction from courts considering
claims of insufficient or abusive scheduling is clear: Don't
cook the books (or more appropriately, the software) or you
will suffer the consequences.
By Philip R. White
My young son likes to remind me of the advice given to his
favorite superhero, Spiderman: "with great power comes
great responsibility." The same is true for construction
schedulers.
In the era of the personal computer, great advances in scheduling
capability have made the schedule a major element of any significant
construction project. Unfortunately, this increased capability
is sometimes abused by owners and contractors when a project
becomes troubled. Although "creative" scheduling
is only beginning to receive the attention of the courts,
courts that have spoken on the subject have reminded the party
with scheduling responsibility that the power of computers
and the latest scheduling software comes with the requirement
that it be used responsibly and in accordance with the contract.
Recent cases have awarded damages to a contractor for poor
scheduling by a public owner and have affirmed the termination
of a contractor for poor scheduling practices.
For example, in R.W. Granger & Sons, Inc. v. City School
District of Albany, the court held an owner responsible for
failing to fully discharge its scheduling responsibilities.
In that case, the owner terminated the contractor on a multiple
prime school project for failure to progress the work in a
timely manner. The contractor defended on the basis that the
owner's termination was wrongful because of its failure to
prepare adequate construction schedules and to coordinate
the work of the prime contractors. The court agreed with the
contractor and awarded $1.4 million in damages to the contractor
for the wrongful termination. Unfortunately, the court did
not elaborate on the deficiencies in the owner's scheduling
effort.
While this is only one example of how courts have dealt with
scheduling deficiencies, it reflects a willingness to authorize
the ultimate sanction: Termination for cause. Given the usefulness
of good schedule practices and the potentially draconian consequences
of not using them, all participants in the construction process
are well advised to allocate enough resources to make the
most out of this tool and to avoid manipulation of the schedule
to achieve a predetermined outcome.
The contract documents for many sophisticated projects require
a baseline CPM schedule and periodic updates. Owners and their
financial backers are concerned to see that the project is
going to be built in a reasonable period of time and to have
a tool to reliably monitor progress. Contractors are planning
their work efficiently and creating one of several project
controls needed to manage the construction process. However,
the schedule has come to serve as a legal record of project
progress, the timeliness of progress payments and disruptions
to the planned sequence and durations of specific tasks. As
a result, an adversarial approach to scheduling often evolves
and the players turn to "creative" scheduling techniques.
Although an exhaustive list of scheduling abuses would fill
more space than this column permits, here are a few common
examples. With baseline schedules, some abuses are use of
leads and lags, failure to resource load and use of multiple
calendars. With update schedules, some abuses are use of logic
overrides, disguising of logic changes, addition and/or subtraction
of physical or preferential restraints and colorful presentations
not linked to underlying scheduling data.
The difficulties presented by the use of these techniques
are compounded by the problems involved in uncovering their
use. Evidence that a scheduler has used one or more of these
techniques is often buried deep in the electronic scheduling
files. It seldom appears on printouts of the schedule. Items
that involve change - like those used in the update schedules
- often can only be found by running time consuming comparisons
between the update and baseline schedules or a previous update.
This involves a level of scheduling sophistication that participants
without schedule responsibility generally lack. Finally, the
more subtle abuses require the attention of a scheduler experienced
in the kind of project involved - also an expense most projects
cannot afford.
Unfortunately, there is no silver bullet for the problem
of scheduling abuse. The decisions noted above ought to serve
as a deterrent to those considering abusive tactics. However,
there are a few basic things that should limit the spread
and efficacy of these techniques:
- Even parties without scheduling responsibility should
allocate resources to scheduling to permit adequate evaluation
of baseline schedules and to carefully review updates.
- Schedule specifications should prohibit the electronic
writing over (destruction) of official schedules communicated
among the parties.
- Schedule information should be exchanged in "read
only" format.
The main thing to remember is that forewarned is forearmed
and to keep abreast of developments in the scheduling world.
A problem that is avoided early in the project is less likely
to lead to costly claims at the end.
Philip R. White is chairman of the construction
practice group of Sills Cummis Epstein & Gross P.C. in
Newark, N.J.
|