|
How to Avoid or Manage Project Delays
The financial ramifications of
a delayed project can be considerable for owners and contractors
alike. For each, time - as the often cited cliché provides
- is money.
By Burt P. Natkins, Esq.
Whether large or small, construction projects are fraught
with many unique and varied risks. Construction-related risks
may range from financial risks to personal injury risks. Indeed,
no project participant is ever completely insulated from these
risks and their potentially devastating consequences. A full
understanding of the nature of these risks and the means to
adequately manage them should be an overriding objective of
all the construction project participants.
Project delay, for example, is a stark, if inescapable, reality
common to the construction industry. Unnecessarily long and
disruptive delays can literally turn an otherwise profitable
project into a financially ruinous undertaking. Avoiding delays,
or limiting their duration and managing their unwanted effect,
is therefore often critical in ensuring a project's ultimate
success.
A full appreciation of the nature and scope of time-related
risks is, unfortunately, of little value if it is not used
to establish a commonsense, workable program to manage those
risks. The mere existence of such a program, however, does
not alone suffice. To be truly effective, the loss avoidance
and loss protection initiatives of the program must be strictly
and timely implemented and followed. Otherwise, claims may
be waived and contractual rights may be forever lost.
Some key program measures for avoiding, limiting or managing
project delays should include:
- Review of the entire contract (including all attachments
and the general and supplementary conditions) before its execution,
with particular focus on the notice of claim, request for
time extension, submittal review, and other similar provisions.
A checklist of the key provisions requiring any action or
communication during the performance of the contract should
be created, with copies provided to all involved in the administration
of the contract.
- Review of the design documents once completed for the
purpose of identifying any obvious design deficiencies or
plan inconsistencies. Any problems identified should be resolved
before the underlying work needs to be performed or otherwise
becomes critical to the project schedule.
- Agreement by all of the project participants on the
forms to be used in connection with the routine project transactions,
including submittals, RFIs, change orders, applications for
payment, lien waivers, and daily reports. Such agreement will
minimize the risk of the exchange of incomplete or confusing
information during the project, thereby avoiding delay or
otherwise exacerbating any ongoing delay.
- Full understanding of the dispute resolution and claim
procedures, including their protocols, and a discussion of
that understanding with the other project participants at
the outset of the project. If the parties' understanding of
the protocols is inconsistent with the contract language,
then the contract should be amended. Also, if such procedures
are later required, the contract requirements must be strictly
followed.
- Creation of a standardized project filing system and
record retention policy. Such measures will inevitably improve
the day-to-day project administration and will enhance the
success of any later initiated claim procedure or dispute
resolution if needed.
- Use of the "agreed upon" project documents
effectively. The content of the documents should be of sufficient
detail to ensure their effectiveness in any later initiated
dispute resolution or claim procedure. For example, if a project
should be delayed, the appropriate documents should at the
time of the delay identify the delay, its cause, and its impacts.
- Timely submission or issuance, logging, and tracking
of all RFIs and responses, submittals and responses, change
order requests, quotes, etc.
- Reducing to writing all orally issued field directives
and orders.
- Updating of the project schedule during the course
of the project to document as-built conditions, including
any changes in schedule logic or construction sequences.
- Many project time-related risks share the same characteristic
- they can be substantially mitigated or otherwise avoided
if they are identified and addressed in a timely manner. Accurate
and effective communications among project participants are
critical to ensuring such mitigation or avoidance. Indeed,
the very dangers of failing to communicate timely and effectively
may be the very root of many project delays. A project participant
should therefore develop and implement its risk management
program with that notion in mind.
Burt Natkins is an attorney with
the law firm of Zetlin & De Chiara LLP in New York, N.Y.
|