|
Between Contractors and Subs Should Be
Clear
The best way to handle partial
releases is for the general contractor to give the subcontractor
the opportunity to specifically detail the claims excluded
from the release.
By Thomas D. Czik, Esq.
When drafting and signing releases, general contractors and
subcontractors should make certain that they are not inadvertently
releasing or keeping open claims. Typically, when it makes
a progress payment to a subcontractor, the general contractor
requires the subcontractor to sign a partial release in which
it gives up its right to make a claim against the general
contractor based on the work it performed during that progress
period. The general contractor's goal is to protect itself
against unexpected claims later for the work the subcontractor
performed during that period.
Partial releases, though, are often ambiguous as to the claims
actually being released. If the subcontractor later makes
claim against the general contractor for items, such as indirect
or impact costs for contract or change order work performed
during that period, the parties may end up in a dispute over
whether the subcontractor's claim was covered by the release.
General contractors and subcontractors can prevent these disputes
by specifically excluding claims in the release.
A recent case shows the problems inherent in not itemizing
the claims in the release. A general contractor contracted
with an owner to build a new tennis stadium. The contractor
subcontracted the masonry work. After the project was completed,
the subcontractor sued the contractor for unpaid contract
work and claims for delays and inefficiencies. The contractor
asked the court to rule that the subcontractor was not entitled
to make the claim because the subcontractor had signed partial
releases throughout the progress of the work. The contractor
argued that the subcontractor had plainly waived its right
to payment for extra work as well as the claim. The subcontractor
claimed that the partial releases were only receipts relating
to the specific progress payments owed at the time it submitted
the partial releases and were not general releases.
The partial releases stated they were "expressly limited,
and unconditional, to the extent of, and as covered by, payments
actually received by the subcontractor" through the date
signed. The court found that it was not clear what monies
the partial releases covered and that a trial would be needed
to determine the monies the contractor and subcontractor intended
the partial release to waive. Based on the limiting language
of the partial releases, the court stated it was not "unmistakably
manifested that the subcontractor intended to surrender its
rights to additional monies and such waivers should not be
lightly presumed."
The best way for a general contractor and subcontractor to
handle partial releases is for the general contractor to give
the subcontractor the opportunity to specifically detail the
claims excluded from the release. This benefits the subcontractor
because the subcontractor can reserve the claim, even if the
subcontractor can not calculate the exact dollar amount of
the claim until later.
By allowing the subcontractor to exclude claims in the release,
the contractor is protected from surprise claims. If the subcontractor
later makes claim for an item not listed on the release, it
will be clear to a judge or arbitrator that the subcontractor
had an opportunity to notify the general contractor of the
claim but did not. Also, by giving the subcontractor a chance
to list specific claims, the parties can avoid later disputes
over which claims were and were not covered by the release.
The general contractor should make certain that excepted claims
are detailed. For example, if the subcontractor has a claim
for delay "disruptions" in the work, the subcontractor
should be required to provide details of the events and manner
in which the work was affected.
By preventing surprise claims, the general contractor also
ensures that it is able to comply with any notice provisions
in its contract if the subcontractor's claim should be presented
to the owner. The general contractor should make certain that
the release ties in with the notice of claim requirements
of the subcontract and the contract with the owner. By avoiding
ambiguous releases and including provisions concerning notice
and claims in the subcontract, the general contractor and
subcontractor can protect claims as well as prevent disputes
and later surprises.
Thomas D. Czik is a partner with
Tunstead Schechter & Czik LLP in Jericho, N.Y.
|