|
Dispute Resolution Board Ruling Favors
Contractor
By Henry L. Goldberg and Alex F. Ferrini
Over many years, New York City public works contracts have
been modified to include increasingly onerous provisions governing
the claim process. Often, these procedural provisions seem
designed to penalize the unwary contractor. Such contract
clauses, however, may not always work to the city's advantage.
In a recent decision, the city's Contract Dispute Resolution
Board ruled in favor of a contractor by wielding the procedural
sword against the city. The contractor was hired by the city's
Department of Parks and Recreation to build an asphalt roller
hockey rink. Six months after completion and acceptance of
the work the department - citing the contractor's one-year
warranty obligation - issued a directive claiming that the
asphalt did not meet the project specifications and ordered
the contractor to remove and replace the top asphalt layer
because the surface had become unplayable.
The contractor responded in writing to the directive, stating
that the department had not shown that the work violated the
specifications or was defective in any manner and that the
work ordered should be considered extra work and compensated
as such. After further correspondence and meetings in which
the contractor and the department continued to dispute the
issue, the department's agency chief contracting officer declared
the contractor in default for failing to comply with the directive.
On three separate occasions, the contractor requested a
final determination from the Department of Parks and Recreation
commissioner regarding the declaration of default and the
contractor's claim that the agency's directive ordered work
that was beyond the scope of the contract. The contractor
never received any substantive response. Indeed, the department's
counsel sent a letter to the contractor (one year after the
initial request!) stating that no further action could be
taken by the commissioner. The contractor proceeded to file
its claim with the city Comptroller's office, which denied
it, citing the contractor's failure to comply with the agency
directive to replace the asphalt as a waiver of the claim.
The contractor then appealed the comptroller's decision to
the city's Contract Dispute Resolution Board.
In its argument before the board, the department reiterated
the comptroller's position that the contractor's failure to
comply with the directive was a waiver of any claim for compensation
or for anything else that relate to the agency's declaration
of default. The board rejected this argument and noted that
the contractor had properly followed the required contract
procedures by promptly seeking the commissioner's review of
the directive.
Significantly, the board found that the department did not
follow the procedures set forth in the contract for declaring
a contractor in default. In particular, the contract documents
stated that only the commissioner or his duly authorized representative
may declare a contractor in default and that a default declaration
can only be made if the contractor refuses to proceed with
the work when ordered by the commissioner. Nothing in the
contract documents or correspondence between the parties designated
the agency chief contracting officer or any other department
employee as the duly authorized representative of the commissioner.
Thus, the directive and the default declaration were improper
because the commissioner did not issue them. Further, the
contract also required that all determinations include a reasonable
explanation. In this case the commissioner failed to make
any determination whatsoever, despite the contractor's repeated
requests. In short, the board found that the agency had completely
failed to adhere to its own contract procedures, both in issuing
the directive and in declaring the contractor in default.
In support of its ruling the board recognized that the department's
actions were inherently unfair to the contractor. By improperly
declaring the contractor in default and then completely refusing
to consider the claim (because according to the department
the default could not be appealed to the commissioner), the
department deprived the contractor of its contractual right
to be heard.
While it is somewhat surprising that the board issued a
decision so critical of the city's administration of a contract,
it is gratifying that basic concepts of fairness in the application
and interpretation of contract obligations won the day. Public
owners cannot set notice traps for the unwary while expecting
to be relieved from the strictures of the contract.
The lesson here is obvious: Contractors should continue
to scrupulously follow the procedures outlined in the city's
numerous contract dispute provisions, but at the same time,
should not hesitate to enforce those same provisions against
the city. As demonstrated by the board's decision, following
the rules means the difference between winning and losing
for contractors and the city alike.
Henry L. Goldberg is managing
partner of the law firm of Goldberg & Connolly in Rockville
Center, N.Y.
|