Arthur
Rubinstein is president of Skyline Steel of Brooklyn and
is a past president of the Subcontractors Trade Association
of New York and the Empire State Subcontractors Association.
|
Smoother Payment Terms Can Rein in Project
Bids
Improvements to contract payment
terms can result in enthusiastic and competitive bids by
subcontractors.
by Arthur Rubinstein
The hot topic of discussion
at a recent meeting of a New York Building Congress committee
on construction costs was the concern expressed by real estate
developers that the large number of substantial projects in
the pipeline for the next few years would result in a shortage
of qualified subcontractor bidders at competitive prices.
Maybe it was a good thing that I was present. I told them
how I would handle the problem if I were a developer. The
issue boils down simply to payment terms. I told them, change
the payment terms, and subs will want to work for you at prices
you will find reasonable.
Why are payment terms so important? A subcontractor's volume
of business is limited by its available working capital and
the resulting bonding capacity that it is able to secure.
Increasing that capital and bonding capacity removes many
of the business pressures that subcontractors face and gives
them an opportunity to bid more confidently on jobs.
At the meeting, I outlined for the developers present the
major points that can streamline payment terms and get subcontractors
on board.
First, developers should commit to pay monthly requisitions
within two weeks, without fail. Today, we submit requisitions
and typically get promised payment no sooner than four weeks
- a timeline that often stretches to five or six weeks. This
is a basic professional courtesy that can go a long way toward
making the owner-sub relationship smoother.
Second, developers should adopt and implement equitable retainage
terms for contract expenditures. One example would be retaining
5 percent of the first 50 percent of the contract, but not
keeping additional retainage afterwards.
Upon substantial completion of the work, the owner should
promptly reduce the retention amount by half. And once the
subcontractor's punch list is completed, pay the retention
balance in full and without delay.
Third, the owner should commit to assigning project team
members at both the developer and construction manager level
to be responsible for reviewing, negotiating, and resolving
change orders. Owners should commit to resolving change orders
within 30 days in order to allow for payment of the balances
during the next requisition cycle.
These are not "pie-in-the-sky" steps, but rather
can be implemented quickly and without great duress for the
owner. A developer adopting this program would have no shortage
of enthusiastic bidders, and would reap economic benefits
far greater than the relative costs of added staff and accelerated
"drawdown" of construction loans.
If the payment program I've outlined were implemented by
all major developers in New York City, it would increase the
available working capital and bonding capacity for subcontractor
companies. Those companies in turn would be able to meet the
market's needs, benefiting subcontractors, contractors, and
developers - and the real estate and construction industries
as a whole.
|