|
New Insurance Options for Complex Site
Cleanups
by Gregory Steinman
Blended finite risk programs offer a new twist on insurance
coverage for contaminated sites - a way to smoothly fund
the project costs and at the same time cover the full tab
for known and unknown cleanup liabilities.
The demolition of the building went as planned. The asbestos
and foundation were removed and transported to a disposal
site.
Removal of the contaminated soils was the next step. However,
the New York City developer was not expecting to discover
12 underground storage tanks, 500 to 1,000 gallons each, suspected
to contain heating fuel oil. By law, it had to report this
finding to a state regulatory agency, which required removal
of the tanks as part of the soil remediation - adding $250,000
to the cost of cleaning up the site.
The trouble didn't end there. When the developer had the
tanks removed, oil constituents in the soil volatized into
the air, creating a noxious odor. Adjoining businesses claimed
that the odor forced them to shut down, adding $750,000 in
restitution costs.
The bad news kept coming. During excavation of soil to install
barriers that would prevent residual contamination from migrating
off-site, workers encountered an unknown contamination plume
migrating onto the developer's property. They eventually determined
that the contamination was PERC, a solvent used in dry cleaning
operations, which presented trouble on two levels - not only
did the developer have to report and delineate the plume,
but it also had to remediate the constituents.
Due to prolonged remedial negotiations with the state regulatory
agency, these activities caused further construction delays
and resulted in $12 million in added project costs.
The original contract budget of $20 million grew to $33 million
after all of the changes.
Such environmental liabilities present a major risk management
challenge to today's construction industry. Prior to beginning
a project, it is imperative to identify environmental exposures
and implement effective means to manage and mitigate the risks.
In a typical project, the discovery of additional or unknown
contamination onsite may expose a developer or contractor
to extra costs, damages, and potential litigation in relation
to first and third party liability claims for bodily injury,
property damage, and remediation expense. The risk of cost
overruns is high.
One way for developers and contractors to manage these types
of environmental risks is through a formalized self-insurance
mechanism, commonly referred to as a blended finite risk program.
These blended programs take traditional risk transfer insurance
and discounted funding mechanisms for known liabilities and
combine the two elements into a long-term project financing
commitment.
The program strictly earmarks funds for the cleanup of site
contamination liabilities, assuring that money will be dedicated
to specific mitigation or remediation tasks, while adding
risk transfer coverage for unknown liabilities. The setup
is particularly useful on complex, multiyear projects.
While standard blended finite risk programs typically cover
costs of mitigating existing or known contamination liabilities,
your insurance provider can tailor the plan to include coverage
for losses associated with the discovery of unknown environmental
liabilities on the same site. Each program can be individually
structured to a project's needs.
In the case above, the developer hired a contractor for the
$20 million demolition and remediation effort, with the developer
assuming full responsibility for additional costs. The developer
chose a blended finite risk program.
The program entailed the developer still paying $20 million.
It was divided into a "premium" of $16 million to
cover the known tasks - essentially an escrow-style pay-up
of funds that were used to pay project costs - and $4 million
for risk transfer coverage, which provided $40 million in
excess limits to pay for unforeseen project costs.
The developer ended up capping costs at $20 million, while
the blended program covered the additional $13 million in
remediation costs. In other words, the developer had prepared
for the misfortune that befell his project.
While there are other insurance options that project participants
can use to address these types of problems - such as remediation
stop-loss or "cost cap" policies - these plans have
limited terms and do not trigger the funding discounts in
the blended program.
The funded balance in a blended program has one other advantage
- it can satisfy investor, financial institution, buyer, and
seller concerns about a project's financing.
|