|
New Power Facilities for Long Island, New
Jersey
A 350-MW plant on Long Island is
close to a construction start. Also, construction on a methane
gas-fueled facility in Columbus, N.J., is on a fast track.
Landfill
Gas a Moneymaker
Officials in Burlington County, N.J., are hoping to turn
an environmental liability into a financial gain as they move
toward a technology that will convert gas released by the
county landfill into usable electric power.
Construction began in March on a 7.1-MW power plant, which
will use methane gas recovered from the landfill in Columbus.
And while a portion of the energy produced will be used to
power the county's 550-acre resource recovery complex, the
remainder will be sold back into the state's power supply
grid.
The county expects to bring in $61.2 million in revenue throughout
the duration of a 20-year contract from power sold to the
grid.
"This was a very attractive idea from an economic standpoint,"
says Mary Pat Robbie, director of the county's Resource Conservation
Department.
GREYHAWK of Woodbury, N.Y., is the construction manager for
DCO Energy of Atlantic City, which designed and is building
the $14.6 million plant. DCO also will operate the plant under
the 20-year contract with the county.
The plant will be powered by five engines that were shipped
in from Austria in March. The project team will install the
engines prior to construction of the 6,700-sq-ft enclosure
that will surround them. The team will also install the generator
sets, fuel treatment equipment, transformers, and switchgear,
says Rob Notley, senior project manager with GREYHAWK.
The facility will use about 2,500 cu ft per minute of landfill
gas, which will generate enough energy to power more than
8,000 households.
The first engine will start up in June, and construction
on the entire facility is expected to wrap up in October,
with the remaining four to be running by August, Robbie says.
The first energy produced will power the county's resource
complex, whose energy costs run about $572,000 a year.
"Once we're generating [power] in excess, though, we'll
put it back into the power grid," Robbie says.
Long
Island Power Plant to Start Construction
Construction may soon start on a new 350-MW power plant in
Brookhaven, N.Y., that is expected to generate 10% of Long
Island's electricity needs.
The
Caithness Long Island Energy Center was awaiting permits from
the Brookhaven Department of Buildings and construction is
expected to start this spring, says Donald Miller, a spokesman
for New York-based Caithness Energy, an affiliate of London-based
Caithness Corp.
The firm obtained discretionary approvals at the federal,
state, county, and town levels, including environmental review,
last summer. And the Long Island Power Authority has signed
a 20-year deal for the purchase of 290 MW from Caithness.
Germany's Siemens Power Generation is the construction manager
on the $450 million project, which is expected to have 200
to 300 construction workers onsite and generate $60 to 70
million in local wages and services. Once the plant is completed
in 2009, Siemens will handle operations and maintenance of
the plant for 17 years.
The natural-gas-fired, combined-cycle power plant will be
on a 15-acre site in the South Yaphank community, a large
industrial area inside the Brookhaven Empire Zone, which confers
special business tax incentives to the owner. Caithness reports
that the plant will use oil as a backup fuel source if natural
gas prices rise.
The plant will combine a gas turbine and steam turbine to
make up an integrated thermal cycle, which, along with other
measures, will make the plant 50% more fuel efficient than
existing facilities on Long Island, according to LIPA. Compared
to older power facilities, the plant will release 90% fewer
airborne pollutants and require 95% less water due to a closed
cycle air-cooled condenser.
LIPA selected Caithness in 2004 to build the facility as
part of an energy production expansion plan that includes
a $600 million underwater cable now under construction, which
will import 660 MW of power generated in New Jersey, and a
140-MW offshore wind farm by FPL Energy of Juno Beach, Fla.,
which is still undergoing approval.
Caithness and LIPA are also funding a $150 million community
benefits package, which includes $139 million in payments-in-lieu-of-taxes
to schools and local taxing jurisdictions.
Manhattan
Bridge Project Chugs Along
Rehabilitation work is progressing on the lower deck of the
Manhattan Bridge, and New York City Department of Transportation
officials say Koch Skanska of Carteret, N.J., the contractor,
is on pace to meet a planned October deadline for re-opening
the roadway.
Traffic on the 5,779-ft-long lower roadway of the suspension
bridge that connects Manhattan and Brooklyn was shut down
in October 2006, forcing traffic to be maintained both ways
on the upper roadway, which was replaced in two phases in
1996 and 2003. The span runs 1,470 ft from tower to tower
and 2,920 ft from anchorage to anchorage.
The $829 million reconstruction of the entire bridge began
in 1982 after years of neglect caused considerable deterioration
to the structure, which carries nearly 80,000 vehicles and
320,000 mass transit riders daily on its subway tracks. The
bridge opened in 1909 on a design by Leon Moisseiff.
In addition to the upper roadway work, tasks completed thus
far in the 25-year-old rehabilitation program includes repainting;
re-anchoring of the main suspension cables; replacing the
south transit tracks; and restoration of the colonnade and
Manhattan Plaza structures.
So far, the current $148 million lower roadway reconstruction
has involved the removal of the old roadway and placement
of new steel and grid deck, which started on the Manhattan
side. Though the lower roadway is expected to reopen in October,
the entire phase is scheduled for an April 2008 completion.
Koch Skanska has been offered a $65,000-per-day incentive
by the transportation department for opening the bridge before
October 14, which could net the firm as much as $3.9 million,
according to an agency spokesman. Representatives from Koch
Skanska did not return calls for comment.
Work on the bridge is expected to be completed in 2013 with
a seismic retrofit of the entire structure.
Click
here for more Infrastructure News >>
|