|
Freedom Tower Marks "Second" Groundbreaking
Days after various parties in the downtown redevelopment effort reached an agreement on a new plan for the World Trade Center site, construction finally started on the Freedom Tower.
Tower Work Kicks Off
After more than a year of delays and design modifications,
work on the Freedom Tower at the World Trade Center site is
under way.
The 1,776-ft.-high building is expected to be the tallest
in the nation upon its completion in 2011. As of mid-spring,
it had no committed tenants.
The work started two days after the Port Authority of New
York and New Jersey - owner of the 16-acre site where the
tower and various other buildings will stand - came to an
agreement with New York-based Silverstein Properties, which
had been the leaseholder and developer of most of the complex.
The two sides had jousted for months over timelines, control
of individual projects on the site, and the redevelopment
effort's financing. In addition, state and local officials
from both New York and New Jersey began to question whether
the original arrangement giving Silverstein the reins to rebuild
might delay completion of the entire complex.
The agreement left Silverstein as developer on three of the
planned office towers onsite, while the Port Authority will
take over the Freedom Tower and another tower to the south.
Silverstein, however, will act as a development agent on the
Freedom Tower. The first phase of the $2.1 billion tower entails
10 to 12 months of excavation and foundation work, including
concrete spread footings on rock, rock anchors, and mini-caissons.
New York-based Tishman Construction is leading the effort
as construction manager.
Originally conceived in the master plan created by Daniel
Libeskind, a New York-based architect, the Freedom Tower design
has undergone several modifications. Despite a ceremonial
groundbreaking on July 4, 2004, work did not begin as planned
the following year on the eventual tower design by David Childs
of New York's Skidmore, Owings & Merrill.
Instead, the New York Police Department issued warnings in
April 2005 that it considered the tower's design to be overly
vulnerable to a ground-based terrorist attack, such as a truck
bomb. That warning led to a new round of negotiations between
Silverstein and state leaders. Childs eventually issued a
redesign last summer, which took the police department's concerns
into account by repositioning the building, using new exterior
materials, and fortifying its base.
Under the revised World Trade Center redevelopment plan, the
five office towers would go up by 2012, joining the recently
completed 7 World Trade Center to the north, which Silverstein
built to replace a tower destroyed in the Sept. 11, 2001,
terrorist attacks. Another notable feature on the site, the
World Trade Center transit hub, is also under construction
and scheduled to open in 2009. Sitework also began in March
on a new memorial complex.
Luxury Conversion in Chelsea
The
rush of luxury condominium construction in Manhattan's Chelsea
district is keeping pace with the planned remodeling of another
former commercial building into apartments, an effort that
will be completed later this year.
Four of five stories in the Hugh O'Neill Building on Sixth
Avenue between 20th and 21st Streets, built in 1876, are being
converted into condominiums. The project will also add two
penthouse floors. The building will have 49 units overall.
The project team is restoring the building's original Corinthian
columns and rooftop pediments, while also reconstructing two
domes on the cross-street corners that had been removed during
previous renovations.
New York's VJB Construction is construction manager on the
$35 million job, with Cosentini Associates of New York as
M-E-P engineer, Manhattan-based Goldstein Associates as structural
engineer, and New York-based Cetra/Ruddy as architect.
The team had to design and install a new mechanical system
on the lower residential floors without interrupting existing
retail businesses below, with most of the work taking place
at night. The team also reinforced the structure with steel
beams to hold the additional weight of the penthouse floors.
The structure has 128,152 sq. ft. of ground-floor retail space.
Temple Restoration near Finish
A restoration of Temple Emanu-El, one of the largest synagogues
in the world, is nearing completion on Manhattan's Upper East
Side.
Tishman Interiors, an affiliate of New York-based Tishman
Construction, is construction manager on the $25 million restoration
of the temple's sanctuary, originally built in 1929. The 11,319-sq.-ft.
sanctuary, which allows seating for up to 2,500 people, has
a peak ceiling height of 107 ft., which necessitated a customized
pipe scaffolding system for many restoration tasks.
The project's second phase is slated for completion in August,
and involves cleaning, replicating, and replacing 1,100 different
surfaces, including marble floors, Akoustalith tile, tessere
mosaics, stone walls, wood pews, and stained glass windows.
It also entails installation of a new sound system and an
upgrade to alarm, sprinkler, and electrical systems.
The project team already completed a first phase renovating
the rear of the sanctuary in time for last September's Jewish
holidays. Tishman had built a temporary tunnel to give congregation
members access to the temple during Rosh Hashanah and Yom
Kippur as it prepared other renovation tasks.
Click
here for more Building News >>
|