|
Airport Construction Projects Move Forward
(9/19/01)
by David S. Chartock
Airport construction projects at John F. Kennedy International
Airport (JFK) in Jamaica, N.Y., and Newark International Airport
in Elizabeth, N.J., are proceeding on schedule following their
shutdown along with the nations airports for four days
last week.
The airports were shut down after two hijacked jetliners
attacked the World Trade Center (WTC), one attacked the Pentagon
and a fourth crashed in Pennsylvania on September 11, 2001.
While the shutdown of the nations airports led the
airlines to lay off thousands of workers, curtail their flight
schedules and ask Congress for a bailout, projects and planned
projects at JFK and Newark were up and running again and moving
to make up lost time on their schedules just one week after
the attack on America.
Major projects at JFK include the ongoing work on the International
Arrivals Terminal (IAT), AirTrain and an American Airlines
terminal. A fourth major project, a new United Airlines terminal,
is said to be on schedule.
Ray Finnigan, a manager of construction for the Port Authority
of NY & NJ (PA), said the PAs first concern was
its people. He added that in the aftermath of the devastation
of the WTCs twin towers, Most of our employees
made it out. Only four or five out of our 600-member engineering
department did not make it out.
IAT
JFKs International Arrivals Terminal (IAT), which is
also known as Terminal 4, is a $1.2 billion, design-build-operate-and-maintain
(DBOM), four-level, 1.5-million-sq.-ft. facility that calls
for a 16-gate operation. Plans also allow for expansion to
26 gates along with additional concourse space.
John Babieracki, executive vice president of AMEC Construction
Management Inc. of New York, the projects construction
manager, said IAT is proceeding as planned with the
remaining phase of the project due to be completed by late
spring.
Babieracki also said that the project was only affected insomuch
as the project was shut down along with the airport for four
day.
He added that he does not expect any physical construction
changes to the project as a result of Septembers attack
on America and beefed-up security at the nations airports.
Airlines claiming they will go belly-up wont
affect the airport. What happens with regard to further airport
construction remains to be seen. Some new security measures
have been implemented, but overall, the general publics
reaction to this event and traveling is a subject of concern
for all of the airlines.
AirTrain
AirTrain is a $1.6 billion project that consists of an 8.4-mi.
light rail system. This system includes an on-airport circulator
consisting of a 2-mi. loop in the airports central terminal
area (CTA) with six stations serving the nine existing airline
terminals. There is also a connection to link rental car sites
and the long-term and employee parking lots.
The project also includes expansion to downtown Jamaica and
to Howard Beach, N.Y. AirTrains link at Howard Beach
provides a link to the A subway train. The link there will
consist of an AirTrain station and a new subway station.
The link at Jamaica Station goes further. At Jamaica Station,
the link will provide a true intermodal hub with connections
to and from the MTA/Long Island Rail Road (LIRR), the E, J
and Z trains and 40 bus lines operated by MTA/New York City
Transit (NYCT) and private companies, and an AirTrain station
that will include ticketing and baggage check-in.
AirTrain consists of a complete grade-separated guideway
system with two tracks, most of which will be elevated from
25 ft. to 50 ft based on what had to be crossed over. On the
Van Wyck Expressway, the guideway is elevated 45 ft. to 50
ft. above the highway.
Steve Schultz, a project executive with Slattery Skanska
of Whitestone, N.Y., part of the AirRail Transit Consortium
(ARTC), the projects DBOM entity based in Jamaica, N.Y.,
said the project was impacted by the attacks on the WTC because
a lot of our tradespeople volunteered and went down to assist.
These workers included ironworkers and crane operators.
Schultz said these volunteers returned to the project by
September 18.
He said the temporary shutdown of JFK and volunteers assisting
in the cleanup and rescue operation at the former WTC site
did not delay the AirTrain project. He further pointed out
that the Port Authority Airport Access and construction
staff are intact. We are proceeding with construction.
Elaborating, he added that the only thing that will
change is that there will be tighter security within the airport.
In our project, most of our station construction is on the
airport and near the terminals. We do have some electrical
work and track work continuing in Howard Beach and Jamaica.
The project is proceeding forward. Both the ARTC and
the Port Authority are committed to delivering the project
on time. The Port Authority of NY & NJ has recovered and
resumed normal operations with regard to this project.
William Foley, a resident engineer of construction for the
airport and the project said We are moving along, proceeding
on schedule.
American Airlines
The American Airlines project at JFK, also known as Terminal
8, is a $1.3 billion, 2.2 million-sq.-ft., four-level project.
Anthony Bosco, project director and executive vice president
for VRH Construction in Englewood, N.J., part of the projects
construction management team, said the American Airlines project
at JFK is going forward, adding that the project is funded
by bonds.
With regard to the on-airport project, he noted: We
had a shutdown for four days for security purposes.
He did not want to speculate on whether the projects
design might change as a result of what happened in mid-September,
noting that Those decisions havent been made yet.
With regard to the four-day shutdown, he added: We
can recoup the schedule.
Although still being designed, the planned new United Airlines
terminal is on schedule, according to William Bodouva, president
of William Bodouva Associates, the projects New York-based
architect.
Continental Airlines
The $1.6 billion Global Gateway project at Newark International
Airport is a massive program with projects within the project.
It is a public-private venture between the PA and Continental
Airlines.
Richard Smyth, program principal for Continental Airlines
at Newark, said after the shutdown of Newark in the days proceeding
the attacks at the WTC and Pentagon that My project
is moving full speed ahead. It is a bonded project and we
have the money earmarked for it. After the disaster, we reinforced
our security requirements with tighter checkpoints. There
are no real construction changes planned. We had to make sure
everything was OK to let contractors back to work.
He added that the projects contractors would be back
to work by September 21, 2001.
27.5M Sq.
Ft. Lost; Industry Responds to Need (9/19/01)
The real estate industry in New York has responded quickly
to the immediate need for temporary office space for businesses
displaced by the September 11, 2001 attack on the World Trade
Center (WTC) in lower Manhattan.
In press conferences covering the disaster, New York City
Mayor Rudolph Giuliani said the real estate industry has responded
with leases for 4 million sq. ft. of space for displaced businesses.
Meanwhile, the devastation of the WTC and surrounding area
in the 16-acre affected area resulted in a loss of approximately
27.5 million sq. ft. of commercial space or approximately
20 percent of the downtown office market, according to initial
estimates by Grubb & Ellis.
The available space in Manhattan at the time of the attack
was estimated at about 25.5 million sq. ft., according to
the firm, which added that only a small percentage of this
available space may be in the large floor plate format of
the former WTC and surrounding buildings. Another 22 million
sq. ft. of vacant space is also believed to be available outside
Manhattan in Northern New Jersey and in Nassau, Westchester
and Fairfield counties.
Click here for
more WTC Articles >> |