|
Rebuilding Underground
Top-to-Bottom Rehab Brings Upgrades
to Wall Street Station
by Kyla K. Wilson
New York City Transit's Wall Street station serving the 4
and 5 subway lines is getting a much-needed $48 million makeover
to replace its roof and rehabilitate the interiors.
The
project entails a major reworking of a station at the heart
of Manhattan's Financial District, which required the project
team to ensure that its work did not interfere with enhanced
security measures and operations for nearby institutions such
as the New York Stock Exchange.
The project, which began early last year, was originally
slated to finish in October 2009, but various breaks and breakthroughs
along the way have shaved an entire year off of the schedule.
The transit agency split the main areas of focus into two
contracts, one for replacing the roof structure and the other
for station interiors. The overall goal is to modernize the
station but also recapture its historic feel through extensive
rehabilitation and restoration of details such as the original
wall and floor tile, says Blanko Kleva, program manager for
the transit agency's Capital Program Management division.
"We replicated and restored details so the station will
look more or less like it originally did when it was put in
service," Kleva adds.
The transit unit and its parent agency, the Metropolitan
Transportation Authority, timed the project to take advantage
of train service diversions already planned for other subway
improvement projects, most notably the massive reconstruction
and reconfiguration a few blocks north to create the $880
million Fulton Street Transit Center. Complete service diversions,
with no trains running through the station, were available
on weekends and weeknights on dozens of occasions.
"Having several projects work on the same service diversion
saves support costs and reduces impact on our riders,"
Kleva says. "Our project required service diversions
to replace the structural roof beams and rebuild the platform
edge."
The service diversions also gave the project team a chance
to run at an accelerated pace.
The team already has a leg up with the unexpectedly fast
completion of the roof work, which was supposed to be split
into one phase last year and another this year. Instead, the
project team was able to finish all of the programmed work
last year.
The roof work began in April 2006, with Prude Construction
of Whitestone, N.Y., as general contractor. The effort entailed
replacing 14 steel structural beams, each 20 ft long, which
had been damaged by water intrusion over the years.
"We had to excavate all the way
from street level down to the structural roof of the station,"
Kleva says. "There were many utilities in the way and
there was a lot of coordination."
The roof replacement team also had to manage traffic in the
area because it had to keep one lane of Broadway, the road
above, moving at all times under an agreement reached with
the city's department of transportation.
"There was a combined effort from all the different
agencies," says John Duggan, project engineer for Prude.
Along the way from street to station roof, the team relocated
and replaced utilities and water mains, while also rebuilding
electrical and water service manholes. It also had to support
and maintain some of the utilities that it was not replacing,
such as water mains and gas lines.
One of the biggest obstacles was an 80-ft-long section of
a 16-in-diameter steam main, Kleva says. The main, which services
most of the buildings in the area, runs almost directly above
the roof, creating a tight project area with little room to
maneuver the delivery and installation of the new steel beams
and concrete roof slab.
The team had to remove and then reinstall the steam main,
a job that it could only take on between May and October to
not interrupt the heating seasons.
"We had to coordinate and temporarily support all the
other utilities to get to the steam main," Kleva says.
"Once the steam main was accessible, we had to coordinate
with a specialty contractor working for Con Ed to abate the
steam main before it could be cut out."
The roof project's original schedule envisioned the team
closing the western side of Broadway and working on one part
of the roof during a first phase in summer 2006, and then
returning for a second phase in summer 2007 to work on the
eastern side. But a key decision came in midsummer when the
project team was ahead of schedule on the first phase and
the city transportation department gave the green light to
proceed right away with the second phase.
Various breaks contributed to the speeded-up schedule, such
as receiving better cooperation than anticipated from local
utilities and having a smoother time than planned with the
street work.
Once the team replaced the subway roof, it again had to coordinate
with another specialty contractor approved by Con Ed to install
a new steam main.
Now, a separate contractor team led by Citnalta Construction
of Bohemia, N.Y., is focused on the station improvements,
a soup-to-nuts effort that started last year and will upgrade
all current systems. The work entails the installation of
new lighting, conduits, communication tools, and electrical
distribution rooms, as well as installation of new floor and
wall tiles.
The team is also elevating the 600-ft-long platform ledges
and widening them at the track edges to meet federal Americans
with Disability Act rules. Another major task is pouring a
concrete base under the new porcelain tile floors.
"We are working closely with New York City Transit's
landmarks consultant about approving materials and installing
mock-ups prior to starting work," says Gary Yerganian,
project executive for Citnalta.
Another big hurdle remains finding ways to accommodate the
people who work in the crowded district.
"We have to be considerate with noise issues during
the day and closures of street stairs during our daily construction
operations," Yerganian says. "Delivery of materials
and removal of debris are mostly limited to nights as is the
use of work trains in the station. And DOT permits for the
street are limited, not allowing us many choices for vertical
movement of materials."
Key Players
Owner: New York City Transit
Roof Contractor: Prude Construction, Whitestone, N.Y.
Interior Station Rehabilitation Contractor: Citnalta Construction,
Bohemia, N.Y.
Steel Contractor: Imperial Ironworks, Bronx
Electrical and Communications Contractor: Five Star Electric,
New York
Tile-Marble-Mosaics-Terra Cotta: NY Stone & Ceramic Tile,
New York
|