|
Balancing Act
Delicate Moves Fit New Transit
Hub into Crowded World Trade Center Footprint
by Natalie Keith
Coordinating construction of a $2.2 billion transit center
in a crowded urban environment would present hardship under
most circumstances, but the task of building the World Trade
Center Transportation Hub, set to open in 2009, defies even
conventional standards.
The
project faces exacting space constraints; complicated logistics
that include keeping subway service in operation; intense
public scrutiny of its design and progress; and one of the
world's busiest construction sites, with work on the 2.6-million-sq-ft
Freedom Tower, a chiller plant, and the Sept. 11 memorial
- as well as three new office towers on the way.
"We have to work closely with all of the stakeholders
on a day-to-day basis to reach a consensus on a range of construction
issues," says Steve Plate, director of the Priority Capital
Programs Department for the Port Authority of New York and
New Jersey, which owns the World Trade Center site and will
operate the hub.
The new facility, designed by Santiago Calatrava, a Spanish
architect, will offer passengers from the Port Authority's
PATH transit system an easy transfer point via underground
passageways to the subway system operated by New York City
Transit. The PATH, which ferries passengers 24 hours a day
between various stations in New Jersey and Manhattan, currently
uses a temporary station that opened at the World Trade Center
in 2003 after the original station was destroyed in the terrorist
attacks.
The Calatrava design calls for a soaring arc of steel beams
and glass, which will frame a main hall currently programmed
to be 340 ft long, 112 ft wide, and 111 ft tall, with multiple
levels and a retractable roof. The building will be flooded
with sunlight by day, and glass paving in the plaza and mezzanine
levels will allow some sunlight to filter 70 ft down to the
five tracks below.
The distinctive design will not only be passenger-friendly
but also create a sense of place in Lower Manhattan, says
Rick Bell, president of the New York chapter of the American
Institute of Architects.
"It's not just a gift from a transportation standpoint
- it's creating a great public space," he says. "It
will be interesting to see what happens in that space other
than commuters passing through it."
The hub will house the permanent PATH terminal with a track
and platform level, a mezzanine level, and access to streets
surrounding the World Trade Center site. It will offer underground
pedestrian connections to stations for 13 New York City Transit
subway lines and link to the World Financial Center Ferry
Terminal via a West Street underpass.
The project's significance to the region is hard to overstate,
says Robert Yaro, president of the Regional Plan Association,
a local transportation planning group. The federal government
has given it priority, funding about $1.92 billion of the
project, with the Port Authority providing the remaining $300
million.
When completed, the hub will finally rework a facility that
was confusing, even for seasoned travelers, Yaro says.
"It was never designed as a system," Yaro adds.
"There are very difficult connections. Visitors find
it almost impossible to navigate."
Construction Effort Moves Ahead
Construction began in September 2005 on the facility with
Phoenix Constructors JV, a consortium of four major construction
managers: Fluor Enterprises of Irving, Texas; Slattery Skanska,
a division of Skanska USA Civil of New York; Granite Northeast
Construction, a division of Granite Construction of Watsonville,
Calif.; and Bovis Lend Lease of New York. The joint venture
is handling the project on a guaranteed maximum price contract.
Keeping to the schedule is a big task, Plate says. The team
closely evaluates the timing and scope of procurement packages,
reviews designs, and conducts value engineering and constructability
reviews as part of the effort to stay on track.
The budget also presents a major hurdle. A recent memo from
the construction team warned that the current design could
increase the project's costs to $3.4 billion.
"The Port Authority is working closely with Santiago
Calatrava, the design team, and the contractor to explore
all available options, including constructability, staging,
and the sequencing of construction - all of which have the
potential to significantly affect cost - while retaining Calatrava's
signature architectural design," Plate says. "We
are committed to delivering the project on time and on budget."
Tasks completed so far include pre-condition surveys, installation
of test piles, and relocation of PATH utilities and the third
rail within one of the New York City Transit subway line structures.
Other work the project team has finished includes installation
of monitoring instruments and minipile casings along the track's
centerline; relocation of perimeter security fences and a
24-in water main along Vesey Street; and demolition and removal
of portions of an old tunnel structure, which served the PATH's
predecessor, the Hudson & Manhattan trains.
A major task on the team's agenda now is extensive underpinning
for the station box and tube for New York City Transit's 1
subway line. The team has installed minipiles and structural
steel framing within and around the subway structure to provide
support during excavation around it. To date, approximately
150 lin ft of piles have been installed.
"[We're installing] 1,000 lin ft of underpinning in
total," Plate says.
The project team also must coordinate with other work onsite,
including planning for the future office buildings that Silverstein
Properties is developing. The east bathtub, which is being
constructed on the south side of the hub's site, is being
prepared so that construction of two of the office towers
can begin in early 2008.
The construction effort for the bathtub will include fabrication
and installation of 60 slurry wall panels stretching 1,200
lin ft, Plate says.
By year's end, the project team anticipates it also will
have erected 350 lin ft of a north-to-south shear wall to
an elevation of 225 ft, placed 4,900 cu yd of concrete, and
used 50 tons of reinforcing steel. Other upcoming work includes
creation of a new temporary entrance on Vesey Street to allow
for construction of the permanent station in the space now
occupied by its Church Street entrance. Steel erection above
grade should begin next year.
While no decisions have been made on changes to the design
to get the project back to its original budget, Bell says
one aspect the Port Authority could revisit is distribution
of commercial uses.
"I'd like to see more commercial activities on the ground
floor," he adds. "Most of it is on the mezzanine
level."
Bell also says one of the most remarkable features - bringing
natural light to the hub's lower levels - poses a puzzle.
"Bringing light down from the street isn't done often,"
he adds. "Balancing the benefits of bringing natural
light with creating a useable public plaza is a design problem."
Key Players
Owner: Port Authority of New York and New Jersey
Contractor: Phoenix Constructors - Fluor Enterprises; Skanska
USA Civil; Granite Construction; Bovis Lend Lease
Architect: Downtown Design Partnership - STV Inc.; DMJM Harris;
Santiago Calatrava
Program Manager: PB Americas, URS
|