|
High Flying
Three New Projects at Burgeoning Buffalo
Airport
An expanded runway, taxiway improvements,
sound mitigation projects, and a new baggage-handling facility
are all in the works at Buffalo Niagara airport in a bid
to meet a growing passenger load.
by Natalie Keith
As passenger counts continue to rise at Buffalo Niagara International
Airport in Buffalo, N.Y., its operator is embarking on three
projects aimed at addressing the growth and mitigating the
airport's impact on the neighborhood.
The Niagara Frontier Transportation Authority is responding
to unexpectedly robust growth since 1996, when the airport
had 3 million passengers. The airport may serve 5 million
passengers this year, a number the facility previously was
not expected to reach until 2020, said William Vanecek, the
authority's director of aviation.
"We felt the time was right to plan for the future growth
of the airport," he added.
The three projects tackle different aspects of the airport's
operations. They are:
a $36 million project to improve the main runway
and Taxiway A
a $54 million noise-mitigation program
and a $22.5 million, two-story, 60,000-sq.-ft. addition
on the airfield side of the terminal for a baggage-handling
facility.
The project that is furthest along is the runway work, which
has involved resurfacing the entire length of the main runway
and Taxiway A and extending the northeast end of the runway
by 725 ft., resulting in a total runway length of 8,827 ft.
The runway now has 1,000 ft. of safety area at each end, bringing
it into compliance with Federal Aviation Administration standards.
The project - funded 75 percent by the FAA, 12.5 percent
by the New York State Department of Transportation, and 12.5
percent by the Niagara Frontier authority - also involved
rehabilitation of three overpass structures that allow the
runway to bridge airport roads.
By late summer, the runway was reopened to airplanes and
most of the taxiway project had been completed. Final tasks
were being completed this fall.
For the resurfacing effort, project crews managed by DiPizio
Construction of Cheektowaga, N.Y., the general contractor,
milled down 4 in. and then replaced it with a 4-in. asphalt
overlay. The grading effort was a big component, said Russell
Stoll, the authority's director of engineering.
"The project required a lot of earthwork and fill work
to bring the land up to grade to support the resurfacing,"
he added.
The team used 600,000 cu. yd. of fill, said Paul Kowalski,
resident engineer with DiDonato Associates of Buffalo, the
project's architect.
When the main runway was taken out of service, it forced
a modification of flight patterns and resulted in extensive
air traffic over communities not accustomed to coping with
the noise, which generated strong complaints.
The team addressed the concerns
by shortening the timetable for the runway work - originally
scheduled to start April 1 and end Oct. 1 - by instead starting
March 6 and finishing on Aug. 1, shaving a month off of the
schedule. The earlier start also took advantage of the colder
March weather, during which most residents have their windows
closed, said Mark Clark Sr., the Niagara Authority's aviation
planner.
Starting construction a month early altered certain project
approaches. During March, the ground was wet and soft, requiring
the contractor to use a granular material for the embankment
work at the north end of the runway, Vanecek said. The change
actually allowed better compaction of the fill, which reduced
the potential for differential settlement of the material
and increased the useful life of the runway.
The airport's $54 million noise mitigation program aims to
benefit the residents who live along the facility's permanent
flight patterns. The program is just getting under way, using
funding from the FAA and state and local governments, and
is expected to run through 2016.
The project first required FAA approval of a Part 150 Noise
Study of its plan to use both remedial and land-use strategies.
The remedial strategies include a sound-insulation program
for approximately 1,740 houses, two schools, and a church,
nearly all of which are located off the ends of the main runway.
The authority selected C&S Engineers of Syracuse as program
manager from a request for qualifications for the job. C&S
is setting up a schedule prioritized to start on houses with
the highest noise levels.
The
program aims to mitigate about 175 to 200 houses per year
with measures that include adding insulation, drywall, solid
doors, double pane windows, and new or upgraded HVAC systems.
Another element of the program will provide residents outside
of the eligible mitigation zone with information on how to
add soundproofing features to their houses. The airport is
constructing a model home with its standard mitigation modifications
and will make a consultant available to discuss installation
techniques, Clark said.
"We're going to do some outreach to address that issue,"
he added.
Finally, the baggage handling facility is set to begin construction
early next year. The $22.5 million, 60,000-sq.-ft. addition
on the airfield side of the complex will be the third major
expansion of a new terminal building that opened in 1997.
The new facility will address space constraints in the existing
31,000-sq.-ft. baggage-sorting area that arose because of
the addition of new security equipment in the wake of the
Sept. 11 terrorist attacks. The rising passenger counts also
are driving the need for the new facility.
The current space allows federal Transportation Security
Administration workers to process 750 bags per hour, but the
new system would let them process 2,700 bags per hour.
The authority was sorting through responses to a request
for proposals this fall and expected to select a contractor
by January. The project is expected to wrap up in spring 2008.
"We're doing the project on a design-build basis to
speed up the process," Vanecek said.
Key Players
Owner: Buffalo Niagara
International Airport, Buffalo, N.Y.
Developer: Niagara Frontier
Transportation Authority, Buffalo
Runway Architect-Designer:
DiDonato Associates, Buffalo
Runway Contractor: DiPizio
Construction, Cheektowaga, N.Y.
Noise Mitigation Program Manager:
C&S Engineers, Syracuse
|