Long Road
Williamsburg Bridge Rehab Epic Close to
End
A multicontract journey for the
rehabilitation of the 103-year-old Williamsburg Bridge crossing
the East River is edging toward completion as work continues
on the eighth and final contract.
by Adrian MacDonald
After more than two decades
of reconstruction work, the Williamsburg Bridge connecting
Brooklyn and Manhattan is finally nearing the day when it
no longer will wear layers of scaffolding.
Virtually every component of the 1903 structure, long neglected
until the multiyear rehabilitation effort begun in the late
1980s, has been replaced or rehabilitated.
"The bridge was built for the pre-traffic era,"
said Hasan Ahmed, director of the city Department of Transportation's
bureau overseeing the East River bridges. Now, the span is
among the most heavily traveled in the city, with 100,000
vehicles on eight traffic lanes and 110,000 passengers each
day on two subway lines.
While seldom spoken of in the reverent tones reserved for
the famous Brooklyn Bridge to the south, the Williamsburg
is structurally the strongest of the four East River crossings
that the city agency oversees, said Terry Daly, senior vice
president for Koch Skanska of Carteret, N.J., the contractor
on the eighth and final phase of the rehabilitation effort.
The city agency also maintains the Manhattan, Brooklyn, and
Queensboro bridges.
Despite the Williamsburg's robust structure, it had fallen
into disrepair over the years. There were even designs for
a replacement bridge before the state Department of Transportation,
which oversaw the bridge until about 1989, let the first rehabilitation
contract in 1987.
The
state oversaw the first three contracts, before the city transportation
agency took over and issued four additional contracts in the
ensuing years that totaled $741 million in construction costs
and involved a rehabilitation of the cable suspension system;
reconstruction of roadways, piers, and columns; and replacement
of subway tracks, signals, and power systems.
Work on the $173 million final contract began in early 2003
with Koch Skanska, a unit of Skanska USA Civil of Whitestone,
N.Y., tasked with strengthening the bridge's main steel support
structures.
While Koch Skanska achieved substantial completion earlier
this year, steel repairs, smaller seismic upgrades, and reconfiguration
of lanes and dividers to introduce a new traffic flow system
will keep the contractor busy for another year.
The Williamsburg is unique among suspension bridges worldwide
because it has suspender cables only on the main span between
the towers. Its outer end spans independently rely on supporting
piers - an oddball design that has required various fixes
over the years, including work in the current final contract.
A more conventional design would use suspension cables for
the whole bridge.
The uniqueness lies in a miscalculation by the original engineers,
who chose to support the end spans independently in an attempt
to save money, Daly said.
But when the original bridge construction finished, its designers
realized the end spans weren't strong enough. They added two
more intermediate piers - forfeiting the anticipated savings,
Daly said.
"If you took away the rest of the bridge, each end span
would stand alone as a bridge unto itself," he added.
The final contract's extensive work on those piers could
have taken only eight months instead of the planned 4.5-year
schedule if the city had the luxury of closing the bridge,
Daly said. But the flow of vehicle and train traffic has been
maintained throughout.
"Anywhere outside New York City it's cheaper to close
the bridge," Ahmed said. "But here you have the
user cost. Closing the bridge just isn't an option."
The contractors also didn't have the luxury of time. Unlike
previous contracts on the bridge that offered bonuses for
contractors to complete work ahead of schedule when tasks
involved all-day lane closures, the final contract only involves
offpeak closures - and thus no incentives. But all contracts,
including the current one, apply penalties if the team does
not hit project milestones on schedule.
"There were seven different liquidated damage penalties
in the contract and no incentive bonuses," Daly added.
Shoring Up with New Steel Work
The final contract has focused on the steel support structures
in the main towers, end-span piers, and stiffening trusses.
It also has miscellaneous work such as adjusting and upgrading
cables, painting trusses, and renovating "comfort stations"
on the pedestrian walkway.
Rehabilitating the main towers was a primary chore. Over
the course of a century of increasing loads, stress on the
tops of the towers - which support the main suspension cable
- had bent them inward toward the bridge center, Daly said.
While it would have been cheaper to replace the towers, that
would have required closing the span, Ahmed said. Instead,
the engineering team devised a way to strengthen the towers
with steel plates.
The design placed the steel plates on the river-facing side
of the main towers to compensate for the compression load.
It also called for "pre-loading" the steel by having
the installers curve each plate outward in the center by 4
to 6 in., then bolt them incrementally from the outside toward
the middle.
"That helps engage some of the compression load earlier,"
Daly said.
Koch Skanska custom-cut every plate for its location, using
wood templates. To get the plates into place, the team had
a crane lift them in pairs weighing about 3,000 lbs. to a
hoist and delivery track system built on the side of the towers.
The plates had to match 21,000 existing rivet holes.
Another major feature was work on the intermediate piers.
The design team found it could completely replace these piers
without disrupting traffic by cautiously removing only a few
steel members at a time. However, the bridge's unusual design
required special attention to the main bearings, which are
located under the roadway inside the main towers.
"Koch Skanska does a lot of bridge bearing work, and
this is definitely the most complicated bearing we've ever
worked on," Daly said.
The bearings and main river piers for the end spans are located
in the same towers that anchor the suspension cables for the
center span, Ahmed said.
To support the bridge structure during the process of replacing
the original bearings and river piers with larger and stronger
ones, ironworkers constructed a temporary jacking tower around
each pier inside the main towers. The temporary tower allowed
crews to jack up the bridge surface just enough to "see
daylight" and replace the bearing, said Douglas Reese,
resident engineer on the project with Greenman-Pedersen of
Babylon, N.Y.
"The drawings only give theoretical load numbers for
the bearings," he added. "But the actual load differs.
You measure as you go. We have gauges on all the temporary
jacks to measure pressure in the jack and determine the actual
load at the bearing location."
The new multirotational pot bearings have sliding capability,
which can counter seismic movement in the bridge joints, Reese
said.
Many Tasks Beyond Heavy Lifting
While ironwork formed the heavy part of the final contract,
the single biggest task in terms of budget was a $50 million
repainting effort on two stiffening trusses, Daly said. The
2,800-ft. long steel support trusses run the length of the
bridge on either side with X-shaped members.
Daily said the painting job required sandblasting of existing
lead paint and dust containment to meet environmental regulations
through a complex network of tarps on scaffolding and a vacuum
system that created negative air pressure in the work area.
The system had 11 compressors with a combined capacity of
18,000 cu. ft. of air per minute.
The containment system also required closing lanes on either
side of the truss, cutting the bridge's traffic capacity in
half.
"The trusses are built tight to the road," Daly
said.
The city gave the contractor 176 days to blast and repaint
both trusses, with a liquidated damage penalty of $50,000
for each day it fell behind schedule. The team ran a 24-hour,
7-day-a-week schedule, and ultimately finished nine days early.
Key Players
Owner: New York City
Department of Transportation
General Contractor: Koch
Skanska, Carteret, N.J.
Resident Engineer: Greenman-Pedersen,
Babylon, N.Y.
Designer: Parsons Transportation
Group, New York
Engineering Consultant:
Siefert Associates, Naugatuck, Conn.
Steel Fabricator: Michelman-Cancelliere
Iron Works, Bath, Pa.
Steel Erector: Northeast
Structural Steel, Yonkers, N.Y.
Electric Contractor:
Welsbach Electric, College Point, N.Y.
|