|
Reconstructed Railyard
Croton-Harmon Facility Makeover
on Fast Track
by Diane Greer
The
busiest railyard in the Metro-North Railroad commuter
rail system is in the midst of a $500 million reconstruction
that will have largely used design-build techniques after
starting out as a traditional bid-build job.
The four-phase effort at the Croton Harmon Rail Yard in Croton-on-Hudson,
N.Y., will modernize the 100-acre yard, replacing 300,000
sq. ft. of existing structures with 500,000 sq. ft. of new
maintenance shops and related facilities.
About $120 million in two phases is already completed, with
the second phase wrapping up this summer. A third phase was
set to start in late summer after Metro-North announced two
design-build project awards - a $280 million contract for
construction of two repair shops and a $12 million contract
for a new wheel-true facility - to a joint venture of Slattery
Skanska of Whitestone, N.Y., Parsons Brinckerhoff of New York,
Edwards and Kelcey of Morristown, N.J., and ECCO III Enterprises
of Yonkers, N.Y.
A growing fleet and outdated facilities spurred the massive
project, said Michael Sickenius, Metro-North's director of
shops, yards, and environment.
"It is our busiest facility, it is too small, it is over
100 years old, and it wasn't designed to maintain the new
types of equipment," he added.
In 2001, Metro-North hired Parsons Brinckerhoff as program
manager to help it develop a master plan to implement the
project. Phased construction is helping to manage the complexity
of the job and avoid disruptions to ongoing operations.
"A lot of utilities and interlocking parts of the operation
had to be examined and moved around to make way for the ultimate
build-out," said Greg Kelly, Northeast general manager
for PB Americas, a unit of Parsons Brinckerhoff, which also
was program manager for the first phase.
Metro-North employed a qualification-based bid process to
select the design-build teams for two of the first three phases.
Sickenius said design-build avoids the potential flaw in a
traditional bid process of a low bidder not being the most
qualified firm to handle the project.
When reviewing technical proposals and RFPs from experienced
contractors, "it jumps right off the page how much they
know," he added.
Metro-North offers a good fit for design-build teams, said
Richard Lombardi, senior project manager for ECCO III, the
general contractor on the first phase.
"Metro-North does a good job with their 30-percent drawings,"
Lombardi said. "They are one of the owners that knows
what they want and they take the guesswork out of design-build."
The streamlined method also helps the team to keep a closer
eye on costs, Lombardi added.
The first phase, started in 2001 and finished in 2003, wasn't
a design-build effort, however. It entailed the initial reconfiguration
of the complex, and Metro-North chose a traditional design-bid-build
approach due to the complications that could have resulted
from excavating in a busy, operational yard without detailed
blueprints.
"We did a lot of detailed design, which was essential
since you have an active yard," Sickenius said. "We
like design-build in a cleaner site."
|
The phase also involved the consolidation of train-servicing
facilities, previously scattered throughout the yard, through
the construction of five new one-stop servicing stations for
10-car trains. Each station is equipped with a fueling pad,
toilet dumping facilities, potable water source, and wayside
power. The team also built an inspection pit beneath one servicing
station.
Another new feature is an innovative piping system to blow
sand - used by locomotives for traction - from two new sanding
towers into the servicing stations, replacing the previous
method of transporting the sand by hand.
The phase also added new electric feeders in order to upgrade
inadequate electrical service that caused intermittent power
losses. The feeders, encased in concrete and running along
the Hudson River, deliver additional power to the yard from
an electrical substation in Ossining, 2 mi. away.
The first phase included one small design-build element -
the construction of a pedestrian overpass. The 200-ft.-long
structure allows employees to traverse the yard without walking
across the tracks.
For the second phase, which began in 2004 and was completed
in June, Metro-North chose the design-build method largely
because of the potential for cost savings, Sickenius said.
Metro-North hired a team of Railroad Construction of Paterson,
N.J., as the general contractor and Gannett Fleming Engineers
and Architects of Harrisburg, Pa., as designer.
By bringing in major team players all at once, the method
also accelerates project delivery, which Sickenius said trims
administrative costs and helps lock in material costs during
today's volatile pricing markets.
"I can cut six months off the procurement cycle,"
he added.
Sickenius said one example of the savings was a suggestion
by Railroad Construction to erect new buildings with prefabricated
insulated metal and precast concrete panels, which go up more
quickly and cheaply than split-face block.
Major elements of the second phase included constructing a
new 12,600-sq.-ft. maintenance-of-way storage facility; a
5,000-sq.-ft. communications building that consolidates feeds
for computer, fire, security, and communications systems;
an 11,000-sq.-ft. expansion for a materials distribution center;
and the rehabilitation of a substation. The team also built
an onsite stormwater treatment center beneath the yard, with
the water flowing through 4-ft.-diameter pipes into four 50,000-gallon
oil-water separator tanks with 15,000, gallon-per-min. pumps.
The second phase's main purpose, however, was to prepare the
yard for future work. The project team relocated several smaller
buildings, parking lots, and outdoor storage areas to make
way for the construction of two large shops in the next phase,
Sickenius said.
The third phase will also use design-build to construct the
new maintenance shops, one for locomotives and the other for
coaches. The shops will be on the west side of the yard, furthest
from neighbors to reduce noise impacts.
The current coach maintenance shop only accommodates four
train cars, which requires the shop doors to remain open,
even in winter, to accommodate longer trains. The new coach
shop to be constructed in the next phase will hold eight-car
trains.
The team will drive about 1,150 piles to support the new shops.
Soil conditions and the high water table will require most
piles to go down 100 ft.
In some areas of the yard, dirt excavated from the first two
phases will be used to raise the ground level above the 100-year
floodplain in preparation for the new facilities.
When completed, the overall project will have involved the
installation of 14,000 tons of blacktop, 20,000 lin. ft. of
track, and 4,200 ft. of electrical ductwork.
In the final phase, the project team will demolish the old
maintenance shop and will construct a new shop designed to
service electric cars. In all likelihood the final phase will
use design-build, Sickenius said.
"Some people have the perception that with design-build,
you just turn it over and the contractors do the job,"
he added. "We have just as much interest and involvement
as you do with traditional design-bid-build."
Key Players
Phase 1
Owner: Metro-North Railroad
General Contractor, Steel, Concrete:
ECCO III Enterprises, Yonkers, N.Y.
Design/Structural Engineer:
Parsons Brinckerhoff, New York; Gannett Fleming Engineers
and Architects, Harrisburg, Pa.
Architect: Sowinski Sullivan,
Sparta, N.J.
Site Engineer: DMJM +
Harris, New York
Phase 2
General Contractor-Steel-Foundation:
Railroad Construction, Paterson, N.J. (and affiliates -
RCC Pile & Foundation and RCC Fabricators)
Designer: Gannett Fleming
Engineers and Architects, Harrisburg, Pa.
Architect: diDomenico
+ Partners, New York
Engineering Consultant:
STV Inc., New York; DMJM + Harris, New York
Concrete: Architectural
Precast, Burlington, Ky.
Electric: Verde Electric,
Tuckahoe, N.Y.; Aurora Electric, Long Island City, N.Y.
|