|
Multiphase Upgrade
Stony Brook Hospital Undergoes
a Major Overhaul
by Lynne Viccaro O'Leary
A
$300 million capital program is transforming nearly every
corner of the Stony Brook University Hospital campus in Stony
Brook, N.Y.
The hospital's modernization program, which entails both the
renovation of existing space as well as new construction,
began four years ago and is hitting a turning point in 2006.
The institution is nearing completion of a new building in
September and just broke ground in April on the central project
of the multiyear plan - adding 150,000 sq. ft. in a new wing
and renovating another 150,000 sq. ft. of the main hospital
building.
Throughout the effort, the institution has been careful to
keep current health care trends in mind, particularly with
regard to patient comfort, said Jane Franz, chief planning
officer for the hospital.
"Studies have shown that patients respond much better
to treatment in an environment with more natural lighting,
for example, than those where only clinical needs are addressed,"
she said.
The capital program's expansive scope allowed the institution
to take a longer view but required a careful phasing plan,
said Neil Heyman, project executive for Gilbane Building of
Providence, R.I., the construction manager on the effort.
"The critical focus of the project phasing plan took
years to formulate," he said. "The key goal was
to maintain ongoing operations and services of the hospital
while sustaining the balance of the construction activities."
The hospital put together a core 15-person group - including
representatives from the hospital, architect, and construction
manager - to develop and implement the phasing plan, which
has included erecting temporary barricades, partitions, and
enclosure bridges to allow staff and patients to weave through
corridors of the existing hospital to avoid areas under construction.
The program got under way in August 2002 with initial renovations,
Heyman said. Among the items completed since then are the
enclosure of an exterior patio structure, expansion of cafeteria
and dining services spaces, and a full rehabilitation and
renovation of 170,000 sq. ft. for an inpatient orthopedic
surgery center.
Other work in the early years entailed renovations to 55,000
sq. ft. of the Heart Center - a job handled by ACC Construction
of New York as general contractor - as well as five cardiac
catheterization laboratories, 23 recovery beds, a 10-bed Critical
Care Unit, and a 23-bed, step-down unit. The team also added
a 2,000-KW emergency generator, expanded the emergency department
by 7,500 sq. ft., rerouted the main entry roads on the campus,
and added a two-story parking structure - complete with a
new helipad on its roof.
New Ambulatory Care Pavilion
Among the major current efforts is the construction of a
new ambulatory care pavilion that is slated to open in September.
Pavlak Construction of Hauppauge, N.Y., broke ground in the
fall of 2004 on the 65,000-sq.-ft. building that will add
several new features to the campus.
A primary component of the new $25 million building is the
Long Island Cancer Center, which includes the Carol M. Baldwin
Breast Care Center and spaces for outpatient medical and surgical
oncology, outpatient pediatric oncology, and cancer support
services. The pavilion will also house a new outpatient imaging
center and pain management services.
The pavilion, which stands on a pile and spread-footing foundation,
required extensive sitework to add a new utility infrastructure,
concrete sidewalks, and asphalt paving. Clad in an aluminum
curtain wall system consisting of metal panels, masonry, and
stone, the space incorporates various design materials, such
as sheet vinyl, terrazzo tile, glass tile wall, onyx tile
wall, wood finish wall, wood ceilings, vinyl wall coverings,
and custom millwork, said Tomas Alvarez, design principal
with Cannon Design of Grand Island, N.Y., which was architect
for the facility.
Alvarez said the hospital wanted the building to have the
flexible space functions of a modern facility.
"The design team developed a clinical core area that
promotes flexibility, and then wrapped this core area in a
glass and metal 'necklace' of public spaces," he added.
"We designed the waiting areas with large windows around
the perimeter of the building so patients could look out at
nature."
But the hospital also wanted the building to be aesthetically
consistent with the rest of the modernization project and
overall campus. It especially sought a visual connection between
the main building and the ambulatory facility.
"The exterior façade served as a 'dress rehearsal'
for the main building," he added. "We wanted to
ensure that there was a unifying design theme and that the
two buildings will have a dialogue."
With an eye toward the future, the design also has to accommodate
the changing needs of the hospital, said Robin Cibrano, project
principal on the effort for Cannon Design. For instance, the
design called for back office space to have removable panels
to accommodate current and future imaging technologies.
|
Major Upgrade to the Main Building
As work wraps up on the ambulatory facility, construction
is taking off on the $120 million centerpiece effort, which
broke ground in April. The project will first entail constructing
a new addition and three-story wing and then shift to renovating
and upgrading the main hospital building's lobby and surgical
suite.
The expansion and renovation aims to transform parts of the
building that were not people-friendly, Cibrano said.
"It was a typical hospital - there wasn't a lot of light,
air, or space to feel comfortable," he said. "We
wanted to create an environment that was more pleasant for
waiting patients and families through the use of natural light
and comfortable furnishings."
Upon its completion in 2008, the new space will house the
emergency department and a new Women and Infants' Center with
a neonatal intensive care unit, labor and delivery rooms,
antepartum and postpartum units, and newborn nurseries.
The 150,000 sq. ft. of new construction includes the addition
of 10 operating rooms and expansion of the emergency room
unit to accommodate minimally invasive surgical equipment
and emerging imaging-assisted procedures.
The effort will later involve rebuilding the hospital lobby
and surgical suite in their existing locations, a challenging
task because the suite is beneath the main entry's circular
drive, which will require significant excavation in front
of the hospital.
Although the hospital campus is in a suburban setting, the
project team is approaching the effort as if it were an inner-city
job because of the phasing and space constraints, Gilbane's
Heyman said.
"Accessibility for the patients, staff, and visitors
was a particular challenge for the core group," he added.
"There is only one entrance [to the hospital] other than
the one to the emergency department. We had to close down
the main entrance, creating the need for a prefabricated pedestrian
bridge."
Heyman said the effort has involved an extensive amount of
excavation and basic logistics.
"We tunneled underground, put the bridge in place, and
connected it to the parking garage 250 ft. away," he
said. "Then, we built a new structure around the temporary
bridge and another temporary enclosure where the original
entrance was."
The team also had to create temporary patient drop-off zones.
It was slated to finish all of the temporary structures in
early summer.
The main building's original design has posed a major project
hurdle during all of the sitework, in part because the existing
topography is tiered, Heyman said. The original structure
forms an inverted pyramid below grade.
"For example, the new operating room suite is one story
below grade, immediately adjacent to 10 existing operating
room suites," he added. "We needed to punch through
the existing foundation wall in 20 places in order to connect
them, all while the OR suites are currently in service."
During all of the renovation and upgrade work, the phasing
plan is ensuring that the hospital continues operating normally,
Heyman said. It is also keeping the projects moving along
a rapid construction schedule.
"We created three consecutive eight-hour work shifts
over a 24-hour period, which allowed us to do our work while
patients were being taken care of," he added. "What
would normally have taken us three weeks to complete only
took one week."
Key Players
Owner: Stony Brook University
Hospital
Master Planner: KMD Architects,
San Francisco
Construction Manager:
Gilbane Building, Providence, R.I.
Structural Engineer:
Ysrael A. Seinuk, New York
Architect: Cannon Design,
Grand Island, N.Y.
Civil Engineer: Schoor
DePalma, Manalapan, N.J.
Electrical Contractor:
Gordon L. Seaman Electric, Bohemia, N.Y.
General Contractors:
ACC Construction, New York; Pavlak Construction, Hauppauge,
N.Y.
Mechanical Contractor:
Botto Mechanical Corp., Plainview, N.Y.
|