|
Reinvented Landmark
Jersey City Development Reconstructs
a Fortress
by Tom Stabile
A
former hospital complex that was a marvel of its time is being
reshaped into a new $350 million, 2-million-sq.-ft. condominium
complex in Jersey City, N.J.
Metrovest Equities of New York is transforming the former
Jersey City Medical Center, which is listed as both a state
and national historic landmark, into the Beacon, a complex
where each building - all to be named after historic movie
theaters - will be fully restored on the exterior and rebuilt
on the interior.
"The conversion involves a gut rehab of all the buildings,"
said George Filopoulos, president of Metrovest. "It is
the largest historic restoration in the state of New Jersey."
The medical campus was a monumental architectural accomplishment
of its time, built during the heart of the Great Depression
under the direction of Frank Hague, the city's legendary mayor
and political boss. Hague, through a friendship with President
Franklin Delano Roosevelt, managed to get the funding and
resources to erect the fortress-like, 10-building, Art Deco
complex, which has eight structures designed by John Rowland
and two by Christian Ziegler, according to Ulana Zakalak,
principal of Zakalak Associates of Red Bank, N.J., the project's
historic preservation consultant.
The complex, which took 13 years to build, included the Margaret
Hague Maternity Hospital, which was once among the nation's
leaders in number of children born. The buildings contain
numerous architectural treasures, said Phil Fierro, executive
vice president of Metrovest.
"The façade has great architectural features
- friezes and steel work on the parapets - and the inside
has wall-to-wall terrazzo, marble walls, and great detail
in the ceilings," he added. "We're really trying
to keep the Art Deco features of that era."
Metrovest purchased the complex in January 2005 and broke
ground shortly thereafter to restore the buildings, some of
which had been vacant for 30 years.
That $120 million initial phase of work entails interior
demolition and environmental abatement of the 22-story Rialto
and the 21-story Capitol, in tandem with restoration of the
exterior façades. Both are slated to open next March.
The phase also involves the renovation of a 25,000-sq.-ft.
pavilion area that links the Rialto and Capitol. The space
will house lobbies and resident amenities serving four buildings
on the complex.
As of May, Metrovest had sold 75 percent of the 315 units
in the two buildings. The units are priced at $300,000 to
$700,000, which Filopoulos said is less than other condominiums
along Jersey City's bustling riverfront sector, where studios
go for the same cost as a one-bedroom unit at the Beacon.
The Beacon's studio, one-bedroom, and two-bedroom units -
many with views of the Manhattan skyline because of the complex's
perch on a high bluff about 2 mi. from the Hudson River -
range from 600 sq. ft. to 3,200 sq. ft. in size.
Both Restoration and Reconstruction
Project crews have their work cut out for them in the dual
effort to preserve the historic features of the complex while
reconstructing the interiors to create the high-end condominium
homes.
The design plan required various approvals from landmarks
authorities and input from the community in what ended up
being a three-year process prior to Metrovest acquiring the
buildings, Filopoulos said. A thorough analysis of the exterior
followed in spring 2005.
"We had our engineers up on scaffolding for months inspecting
every brick," he added.
The team's various demolition, masonry, general construction,
interiors, and steel contractors have been busy over the last
several months replacing exterior bricks, windows, and various
interior structural elements, while also repointing and power-washing
the façade. The team also has restored or reproduced
custom versions of Art Deco-style bricks, terra cotta panels,
granite, wrought iron, steel, marble, and friezes around the
two towers.
The team is coordinating many of the tasks under State Historic
Preservation Office guidelines, a requirement that was part
of Metrovest's development approvals, Zakalak said.
As with any major restoration, surprises abound. In this
case, the buildings held many secret corners, because they
served not only as a hospital but as the place where Mayor
Hague held court for years, Filopoulos said.
"We stumbled across hidden offices," he added.
Subcontractors on the job are uncovering many of the surprises,
said John Miranda, project manager for Global Ironworks, a
structural and miscellaneous steel contractor based in the
Bronx that is fabricating and installing replacement steel
for the first two buildings.
"As they're gutting this building out, we're finding
medical files, letters," he added. "You'll find
all kinds of crazy things in an old hospital."
With early demolition and façade work nearing completion,
the focus in recent months has been the reconstruction of
the interiors, with New York-based Turner Construction, working
from its Somerset, N.J., office, leading the interior project
team on the Rialto and Capitol.
"They did a lot of the demo over the last year, and
our work started in February," said Ed Jenkinson, project
executive for Turner. "It's being stripped down to the
superstructure, and the only thing remaining on the floors
are the elevators and exit stairways. We're doing all of the
windows, elevators, masonry, drywall, and M-E-P work."
The structural rehabilitation work is extensive. Many floors
need patches for uneven portions of the slab where crews had
knocked down masonry interior walls and found troughs beneath
them, Jenkinson said. Other spots had holes where there had
been chutes for mechanical systems, and the roof required
major patches of 30-ft. holes in several sections where crews
had removed old water towers.
Many of the patches involve adding steel, corrugated decking,
and concrete pours, said Miranda, whose contract is about
$1 million. His work includes reinforcement to add new HVAC
units on the roof as well as steel for the amenities space.
The structural work also comes with surprises, such as crews
expecting to find steel beams based on the drawings but instead
finding concrete ones, Miranda added. In some places, the
steel has deteriorated badly because the building had long
been out of use, requiring major reinforcement of floors with
new steel. In other spots, the crews are finding that the
original contractors had inserted hollow walls where full
masonry walls were on the original drawings - requiring the
new team to fix those decades-old issues.
Overall, the two buildings will use 150 tons of steel, Miranda
said. Most of that will enter the buildings by hand and rise
in the complex's oversized elevators because crews cannot
erect an exterior hoist - due to the masonry restoration effort
- and cannot use a standard site crane because it would be
too heavy for the grade-level surface, which stands above
a network of tunnels that linked buildings in the hospital
complex.
Having to bring in steel by hand has created complicated
scheduling logistics for delivering materials to the floors
and also requires crews to splice together smaller steel sections,
Miranda said.
"It's not your normal structural rehab," he added.
"This is a unique project."
A Fully Outfitted Living Community
While the restoration and reconstruction effort is the main
focus, the first phase of the complex set for completion next
spring will also feature the Aqua, a lifestyle and fitness
center that will link to a joint lobby and amenities space
for the Rialto and Capitol.
The center will have a gym, yoga studio, children's playroom,
screening room, indoor pool, hot tubs, saunas, lounge, and
locker rooms. The amenities area will also feature various
spaces built with Art Deco finishes, including a gathering
hall, a catering kitchen, poker room, reading gallery, and
billiards hall. Fierro said some of the rooms will occupy
grand 30-ft.-high halls while others will be more intimate.
"The pool room is Frank Hague's old office, and will
have terrazzo floors and wood paneling," he added.
The complex will also have a rooftop restaurant, 6,000-sq.-ft
terrace, retail shops, and licensed day-care facility, while
the condominium units will have high-end finishes, including
marble in the bathrooms and Pietra Cardosa stone in the kitchen.
The next phase of work is an $80 million effort to add 214
units in buildings dubbed the Mercury and the Orpheum, Metrovest's
Filopoulos said. Those and the remaining six buildings onsite,
which range in height from 10 to 23 stories, all need exterior
restoration. Engineering design work has begun on the 18-story
Mercury and the 20-story Orpheum, he added.
Meanwhile, on the Rialto and Capitol, interior work continued
in late spring, including sheet metal and sprinkler installation
on lower floors. The effort is ramping up, and by October
there will be about 300 construction workers on the site,
Turner's Jenkinson said.
The large crew will have a strong safety focus, Global's
Miranda added, citing an emphasis on reducing work violations.
"They have very strict rules," he said. "Every
piece of steel has to have a stamp on it. Everything has to
be rated."
Key Players
Developer: Metrovest
Equities, New York
Construction Manager:
Turner Construction, New York
Architect: Ismael Leyva
Architects, New York
Structural, Miscellaneous Steel:
Global Ironworks, Bronx
Demolition Contractor:
Bedrock Contracting, Fair Lawn, N.J.
Masonry Contractor: Commodore
Construction, New York
Historic Restoration Consultant:
Zakalak Associates, Red Bank, N.J.
Structural Engineer:
Goldstein Associates, New York
M-E-P Contractor: S.A.
Comunale, Barberton, Ohio
Environmental: Slavco
Construction, Clifton, N.J.
|