|
Historic Justice
Restoration Brings Back Grandeur
of Long Island Courthouse
by Bruce Buckley
The
Old Nassau County Courthouse in Garden City, N.Y., is the
oldest government building in the county and one of the first
public facilities in the United States constructed of reinforced
concrete.
But the 103-year-old building, for which then-New York Gov.
Theodore Roosevelt laid the cornerstone to start construction,
suffered years of historically insensitive additions and renovations,
followed by decades of neglect.
Now, in a $35 million restoration effort that is several
years in the making, crews are peeling back the damage and
breathing life back into the historic structure.
"I've worked here 18 years and I haven't seen anything
rebuilt - I've just seen things deteriorate," said Carol-Lynn
Friedman, chief architect with Nassau County's Department
of Public Works. "This is a project where we are seeing
it go in the other direction. It's coming back."
Work on the project began in 2002 with the restoration of
the two-story, 135,000-sq.-ft. building's signature dome.
Then, after nearly $1 million in demolition, a full restoration
of the courthouse and an adjoining annex began last summer.
When completed next June, the renovation will return the
courthouse to its look and 90,000-sq.-ft. size in 1916 - the
year recognized when it was added to the National Register
of Historic Places in 1978. A glass corridor will also link
the building to a new annex structure also under construction.
The courthouse's renovated space will become the home of
the county Legislature's offices. The $10 million, 25,000-sq.-ft.
annex will house the county executive's offices and a new
legislative chamber.
After the county built a new courthouse in the 1930s, it
began converting the historic structure to an office building,
with partition walls cutting through the original courts to
create workspaces. Taking the courthouse back in time meant
that the project team - led by the LiRo Group of Uniondale,
N.Y., and New York-based Bovis Lend Lease as joint venture
construction manager - had to remove major additions, the
interior partition walls, and multiple ceilings.
From early in the planning stages, the project team realized
it would take a monumental effort to renovate the structure,
but it wasn't until the demolition phase that the full extent
of required work became evident. One of the biggest tasks
involved removing four large additions from the building,
including extensions of historic wings and additional floors
that had been added to loggias.
Friedman said the crews expected to find 28 hidden arches
as they removed additions but found only seven still intact.
"[Earlier crews] had put a second floor on the loggia
and the support was run through the old archways," she
said. "There was no respect for it."
Crews delicately removed the partitions as well as three
ceilings that covered the original ceiling on the main floor.
As they removed each piece, structural stability became more
of an issue. Crews also discovered several structural beams
that they didn't know existed and that needed to be removed.
There were nervous moments, said Larry Blond, project executive
with LiRo Group.
"There were a lot of cracks and no one was sure what
might happen," he added. "We had removed an entire
back wing and had to shore it from basement to ceiling with
a double row of shoring."
The project team also put great effort into preserving one
of the building's architecturally significant elements - a
Ransome method slab. The building has one of the first examples
of the turn-of-the-century technique, which uses a twisted
metal rebar rib that runs across and supports a hollow slab.
The slabs were bulging in spots and required strengthening
so that new mechanical equipment could hang from them. The
crews drilled holes through the slab every 3 ft. on center,
placed an 8-in.-diameter washer on top, and hung a welded
wire mesh along the bottom and sides. In some areas, crews
also added Unistrut-brand metal framing to help support hanging
mechanical units.
"It was quite an effort to come up with something that
helps stabilize the slabs and at the same time gives us a
way to hang our mechanical," Blond said.
The mechanical, electrical, and plumbing designs require
careful coordination to add extensive new systems to the old
structure, such as central air conditioning that is replacing
window units.
Low ceiling heights in the basement forced the team to develop
several designs to hang utilities while maintaining egress
and access requirements. The plan included running some systems
along the building's exterior and through trenches.
The project team topped out the structural renovation work
with the final piece of steel in April. With the building
structurally sound, much of the effort has shifted to restoring
the appearance of the courthouse as it was in 1916.
The restoration effort is touching many parts of the building.
To replace stone that can't be restored, the team is using
cast stone and glass-fiber-reinforced concrete.
Meanwhile, replica wood windows from Marvin are replacing
existing windows, providing the same look with more efficiency.
Crews are also adding EPDM roofing and restoring terra cotta
roofing.
Interior work will include restoring plaster ceilings, wood
finishes, copper work, ceramic tiles, and terrazzo. The interiors
feature several historic pieces, including Tiffany light fixtures
and Works Progress Administration-era murals.
While returning to its 1916 appearance, the historic courthouse
will have a connection to the new two-story annex building
behind it. The link will be a glass curtain wall corridor
that will wrap around a portion of the courthouse's exterior
walls, leaving them visible from the outside.
"We didn't want to overpower the courthouse building,"
said John Gering, managing partner of HLW International in
New York, the project's architect. "We chose the curtain
wall to give it a much lighter feel. It reflects the landscape
and the sky but doesn't fight with the courthouse."
The new annex's cast stone façade also echoes the
exterior of the old courthouse.
County legislators will step into their newly polished spaces
next year. Few of them may appreciate the change as much as
chief architect Friedman, however, who recalls how the building
had deteriorated because her department was one of the courthouse's
last tenants before the renovation project began.
"It's hard to believe the difference this will make,"
she said. "Before, a lot of the beauty was hidden. I've
got much more respect for this building now."
Key Players
Owner: Nassau County
Department of Public Works, Westbury, N.Y.
Program Manager: Carter
& Burgess, New York; Greyhawk North America, Woodbury,
N.Y.
Construction Manager Joint Venture:
Bovis Lend Lease, New York, and LiRo Group, Uniondale, N.Y.
Executive Architect-Engineer:
HLW International, New York
Historical Architect:
John G. Waite Associates Architects, New York
Structural Engineer:
Robert Silman Associates, New York
Mechanical Engineer:
Plus Group Consulting Engineering, New York
Site-Landscape: EDAW,
New York
Survey-Civil-Geotechnical Consultant:
Hirani Engineering & Land Surveying, Mineola,
N.Y.
Environmental: JC Broderick
& Associates, Holbrook, N.Y.
Demolition: Gramercy
Group, Westbury, N.Y.
General Contractor: MA
Angeliades, Long Island City, N.Y.
Mechanical Contractor:
Sav-Mor Mechanical, Ronkonkoma, N.Y.
Plumbing: WHM Plumbing
and Heating Contractors, East Setauket, N.Y.
Electrical: Eldor Contracting,
Holbrook, N.Y.
|